Hide Resource Name on Gantt Bars globally

Microsoft Project

    Sponsored Links

    Next

  • 1. Split Task Question
    I want to split a Gantt chart bar into 3 segments & decide when each segment begins & ends. For example, segment one should begin 06/01/07 and end 06/08/07; segment two should begin 08/16/07 and end 08/23/07, and segment three should begin 05/01/08 and end 06/20/08. (I don't want to define these as different tasks requiring additional rows on the Gantt chart.) Thanks to any Project genius who can help. -- -John M
  • 2. Fixed Works/Flexible Resource Units
    Project 2003, SP2 question: I set up a task of fixed work. Work is set at 40 hours. I enter Resource A at 50%, Project figures out it will take two weeks at 4hrs a day and sets the duration to 10d. All is good. I then enter Actual Work for Resource A. Let's say A works only 2 hours on the first day instead of the alloted 4 hrs. Project then calculates out that Resource A will need to work those other two hours on day 11. Is there anyway to tell Project to leave the duration at 10 and increment the units, at least until a resource hits 100% units. I guess the same holds going the opposite way. If a resource works 8 hours instead of 4, rather than pulling in the duration by a day, I'd rather Project change the units from 50% to 40% (or whatever the correct calculation would be to keep work at 40 hrs and duration at 10 days. Thanks in advance for the help.
  • 3. Max Number of Outline Levels Excel can accept/display
    One of our users is trying to export a large project into excel and she gets an error message that the Max number of Outline levels has exceeded the excel limits. We were wondering what the Max number of outline levels accepted by excel is? Thanks!
  • 4. Motivation
    Hi! I'm our Project Administrator at work and I have someone who has just been told to formally write up their projects in MS Project. They aren't too thrilled with that, because of the time and effort that it takes. But, upper management has asked that his projects be managed this way. He willingly, yet so unwillingly, is allowing me to spend time with him, but I've ended up sitting at his computer and entered his tasks for him - he doesn't seem to want to know even what buttons to push to do certain things - I don't feel that he is learning at all - he needs to physically do it himself, or allow me to spend more time with him to show him the basics and have him ask questions. It may be too early in the game, but I predict the evidence of no more information flowing through his project will reveal his lack of interest in doing this, despite what he has been told. How do I motivate such a person? How do I train them sufficiently as well? The little time that I did spend with him, he kept asking, "Are we done yet?" I'm sure this scenerio is not new to any of you out there. When change comes people tend to resist. I must add that he is in our Research and Development Department - that department is very dynamic and he has a lot on his plate, but I believe that he chooses to put a lot on his plate, and hasn't been told to take on all that is there. Any ideas or feedback welcome! Thx!

Hide Resource Name on Gantt Bars globally

Postby U3RldmUgVmluY2VudA » Sun, 08 Feb 2009 07:00:03 GMT

Is there a way to hide the Resource Name that is displayed next to each Gantt 
bar? I know you can remove the name display on a bar-by-bar, individual 
basis, but is there a global setting that will "not" show resource names for 
the entire project?

TIA,

Steve

Re: Hide Resource Name on Gantt Bars globally

Postby Mike Glen » Sun, 08 Feb 2009 08:22:56 GMT

Hi Steve,

Welcome to this Microsoft Project newsgroup :)

Try Format/Bar Styles... and in the Text tab, delete the entry for Resource 
Names from the "right" cell.

FAQs, companion products and other useful Project information can be seen at 
this web address:  http://www.**--****.com/ 

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See  http://www.**--****.com/ 







Re: Hide Resource Name on Gantt Bars globally

Postby Rod Gill » Sun, 08 Feb 2009 08:26:17 GMT

Yes. Select Format, Bar Styles and remove Resource Names from critical and 
noncritical bars. Better yet create separate Views for each report you need 
to produce rather than formatting and re-formatting the same View.

-- 

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
 http://www.**--****.com/ 









Similar Threads:

1.Ability to change Gantt Bar color based on Resource Name

Is there a way to customize project to display different color bars in Gantt 
based on the resource classification (name)

2.Task Summary view: Resource names above gantt bar?

How do I get the resource names to show above the bar in the task summary 
gantt chart view? They appear for all the sub-tasks when summary task filter 
is not applied, but not on the sumary task bar. 

I want to print out a task summarygantt chart view, but I need to see all 
the resources that are assigned to a particular task summary (we are a small 
organization, there are no more than 6 resources assigned to any task). The 
resource name column is also blank at the summary level.

I have tried the gantt chart wizard, but nothing happens in the summary view.

Thanks
M


-- 
New to MSP
MS Project 2003

3.Howto change bar color globally for a resource

Hi all,

I'm using MS Project Pro 2002 and want to know if I can do something.
I've got a schedule layed out for a project with resources assigned to
tasks. Is it possible to give a resource (my team members) a
particular bar color so when they look at a project they can
immediately see what tasks are theirs? I can set the bar colors/styles
on a bar by bar basis, but this is a pain. What I'd like is to set a
bar color/style for each resource so when I move resources around, the
bar color/styles follow it. Know what I mean?

Thanks in advance for your help,
Doug Farrell

4.Resource Name Display on Gantt Bars

I have selected to display Resource Names as Gantt Bar 
Text.  However, as my resources are loaded (units) at 85%, 
when the resource name is displayed, the percentage is 
also displayed in brackets next to the resource name (i.e. 
John Doe [85%]).  Is there a way to display the resource 
name w/o the percentage (i.e. John Doe) and maintain the 
85% loading (unit) for the resource?
Thanks.

5.HowDoI hide text under a gantt bar when its rolled up in Project

When I display text under the gantt bar, all of the text gets jumbled when I 
roll up the subtasks.  I want to display the text for the sub task but NOT 
display text in the rolled up gantt bar.  Any ideas?  

6. Gantt Chart Wizard (Critical Path) and Bar Name Corruption

7. Show task name next to Gantt bar?

8. change font for task.name and color of gantt bar based on criteria



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 51 guest