Hide Resource Name on Gantt Bars globally

Microsoft Project

    Sponsored Links

    Next

  • 1. Actual Cost vs % Complete using Earned Value
    Hi all, I have a task to build 5 miles of train track in 5 days, for $5000 at $1000/day I have a resource assigned at $125/hr or $1000/day. If after 1 day, I only have 1/2 mile of track laid, then my earned value (BCWP) should be only $500 and my actual cost (ACWP) should be $1000. My resource is based on Fixed Units, my Calculation is set to Automatic and my task is effort driven. I enter the task info, save the baseline and BCWS, BCWP and ACWP are all automatically calculated. For day one, each value is $1000. Great! What I want is to have someone at the jobsite call me at the office and tell me how much actually got done for the day as I already know I spent $1000 for the day. I have tried putting in fields such as Actual Work, % Work Complete, Actual Cost, etc but it seems that % Work Complete and % Complete are the same thing so I never see my BCWP change from $1000 down to $500. How can I set things up or better yet where can I enter in the ACTUAL amount that was done and compare that to what was ACTUALLY spent? Glenn
  • 2. Task 0 and Filename
    I know how to turn on the task 0 being displayed by activating the "show project summary task" via tools-options-view. I also know that I can manually change the Title under file-properties-summary. This will change the Task 0 to match the title. What if I want to go back to the task 0 being displayed as the filename (as though I did not manually place in the title)? I tried clearing out the title and doing a save as, but the old title just keeps getting placed back into the title. I also know I can write some code to change the title everytime a save is done, but why can't I get Task 0 back to being the filename?
  • 3. Pasting MS Project Report
    Can you copy a customized MS Project report and paste it into MS Word? If so, what are the steps invovled? Thanks Dave
  • 4. How do I display where TODAY is on my timeline?
    Is there a convenient way to show my timeline with a line indicating today's date?

Hide Resource Name on Gantt Bars globally

Postby U3RldmUgVmluY2VudA » Sun, 08 Feb 2009 07:00:03 GMT

Is there a way to hide the Resource Name that is displayed next to each Gantt 
bar? I know you can remove the name display on a bar-by-bar, individual 
basis, but is there a global setting that will "not" show resource names for 
the entire project?

TIA,

Steve

Re: Hide Resource Name on Gantt Bars globally

Postby Mike Glen » Sun, 08 Feb 2009 08:22:56 GMT

Hi Steve,

Welcome to this Microsoft Project newsgroup :)

Try Format/Bar Styles... and in the Text tab, delete the entry for Resource 
Names from the "right" cell.

FAQs, companion products and other useful Project information can be seen at 
this web address:  http://www.**--****.com/ 

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See  http://www.**--****.com/ 







Re: Hide Resource Name on Gantt Bars globally

Postby Rod Gill » Sun, 08 Feb 2009 08:26:17 GMT

Yes. Select Format, Bar Styles and remove Resource Names from critical and 
noncritical bars. Better yet create separate Views for each report you need 
to produce rather than formatting and re-formatting the same View.

-- 

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
 http://www.**--****.com/ 









Similar Threads:

1.Ability to change Gantt Bar color based on Resource Name

Is there a way to customize project to display different color bars in Gantt 
based on the resource classification (name)

2.Task Summary view: Resource names above gantt bar?

How do I get the resource names to show above the bar in the task summary 
gantt chart view? They appear for all the sub-tasks when summary task filter 
is not applied, but not on the sumary task bar. 

I want to print out a task summarygantt chart view, but I need to see all 
the resources that are assigned to a particular task summary (we are a small 
organization, there are no more than 6 resources assigned to any task). The 
resource name column is also blank at the summary level.

I have tried the gantt chart wizard, but nothing happens in the summary view.

Thanks
M


-- 
New to MSP
MS Project 2003

3.Howto change bar color globally for a resource

Hi all,

I'm using MS Project Pro 2002 and want to know if I can do something.
I've got a schedule layed out for a project with resources assigned to
tasks. Is it possible to give a resource (my team members) a
particular bar color so when they look at a project they can
immediately see what tasks are theirs? I can set the bar colors/styles
on a bar by bar basis, but this is a pain. What I'd like is to set a
bar color/style for each resource so when I move resources around, the
bar color/styles follow it. Know what I mean?

Thanks in advance for your help,
Doug Farrell

4.Resource Name Display on Gantt Bars

I have selected to display Resource Names as Gantt Bar 
Text.  However, as my resources are loaded (units) at 85%, 
when the resource name is displayed, the percentage is 
also displayed in brackets next to the resource name (i.e. 
John Doe [85%]).  Is there a way to display the resource 
name w/o the percentage (i.e. John Doe) and maintain the 
85% loading (unit) for the resource?
Thanks.

5.HowDoI hide text under a gantt bar when its rolled up in Project

When I display text under the gantt bar, all of the text gets jumbled when I 
roll up the subtasks.  I want to display the text for the sub task but NOT 
display text in the rolled up gantt bar.  Any ideas?  

6. Gantt Chart Wizard (Critical Path) and Bar Name Corruption

7. Show task name next to Gantt bar?

8. change font for task.name and color of gantt bar based on criteria



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 32 guest