Hide Resource Name on Gantt Bars globally

Microsoft Project

    Sponsored Links

    Next

  • 1. Project 2007 Missing Local Cache Cleanup tool option
    I have a user that has on occasion opened Project Professional 2007 (conected to Project Server) then selected Tools on the menubar and the option Local Cache Cleanup is not showing (not that it is grayed out it is missing completely) but the next time she is on her computer and tries the same thing it may show up. Unfortunately, it is intermitant once it is here and sometime it is not. Has anyone had a similar problem, is there a way to access this option other than the drop down menu? Thanks, AmWall
  • 2. Exporting a Project
    I've developed a plan in MS Project but many of the team members do not have MS Project. I've exported to excel, which works fine, except all of the tasks are treated the same, e.g., the heading task looks just like the sub task. I'd like to export the plan to excel in a format that looks just like the plan: I'd like the top level tasks to be bolded, with the sub-tasks indented. Any ideas? Thanks. Paul Peterson.
  • 3. HUGE project file (1.2 GBytes)
    Hi all, I just started managing projects for a company. I've taken over an in flight project, that was managed with an MSProject 2000 plan. The .mpp file is HUGE (1.2 GBytes) and takes forever to manipulate. I have never seen such a huge MSProject file, and have been trying to figure out why it is. The file has 150 tasks, 40 resources and 260 assignments: this should be a small file. This looks like a runaway cause. Can you help me identifying why it has gotten so big, and most importantly, how I can easily shrink it? Thanks Pierre
  • 4. Project Split or Delay tasks
    I have a situation where I need to have a split in work. I have a two week task that will be interrupted for 3 days. However, I will still be 25% allocated on the first task and 75% on the second task. I am having trouble trying to make this work. I am happy for some help. -- Rich
  • 5. Exact formula for %Complete for task with multiple assignments??
    Hi Anybody know the exact formula for %Complete of a task with multiple assignments? This is a more complicated question than it first appears. Internally, the assignment table has no duration field. If you wanted to calculate the duration of an assignment, you would have to iterate through all the assignment detail records and even then the algorithm would be somewhat arbitrary. I suspect the %Complete for a task with multiple assignments is actually based on assignment work and actual-work. Is this true?? Carl

Hide Resource Name on Gantt Bars globally

Postby U3RldmUgVmluY2VudA » Sun, 08 Feb 2009 07:00:03 GMT

Is there a way to hide the Resource Name that is displayed next to each Gantt 
bar? I know you can remove the name display on a bar-by-bar, individual 
basis, but is there a global setting that will "not" show resource names for 
the entire project?

TIA,

Steve

Re: Hide Resource Name on Gantt Bars globally

Postby Mike Glen » Sun, 08 Feb 2009 08:22:56 GMT

Hi Steve,

Welcome to this Microsoft Project newsgroup :)

Try Format/Bar Styles... and in the Text tab, delete the entry for Resource 
Names from the "right" cell.

FAQs, companion products and other useful Project information can be seen at 
this web address:  http://www.**--****.com/ 

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See  http://www.**--****.com/ 







Re: Hide Resource Name on Gantt Bars globally

Postby Rod Gill » Sun, 08 Feb 2009 08:26:17 GMT

Yes. Select Format, Bar Styles and remove Resource Names from critical and 
noncritical bars. Better yet create separate Views for each report you need 
to produce rather than formatting and re-formatting the same View.

-- 

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
 http://www.**--****.com/ 









Similar Threads:

1.Ability to change Gantt Bar color based on Resource Name

Is there a way to customize project to display different color bars in Gantt 
based on the resource classification (name)

2.Task Summary view: Resource names above gantt bar?

How do I get the resource names to show above the bar in the task summary 
gantt chart view? They appear for all the sub-tasks when summary task filter 
is not applied, but not on the sumary task bar. 

I want to print out a task summarygantt chart view, but I need to see all 
the resources that are assigned to a particular task summary (we are a small 
organization, there are no more than 6 resources assigned to any task). The 
resource name column is also blank at the summary level.

I have tried the gantt chart wizard, but nothing happens in the summary view.

Thanks
M


-- 
New to MSP
MS Project 2003

3.Howto change bar color globally for a resource

Hi all,

I'm using MS Project Pro 2002 and want to know if I can do something.
I've got a schedule layed out for a project with resources assigned to
tasks. Is it possible to give a resource (my team members) a
particular bar color so when they look at a project they can
immediately see what tasks are theirs? I can set the bar colors/styles
on a bar by bar basis, but this is a pain. What I'd like is to set a
bar color/style for each resource so when I move resources around, the
bar color/styles follow it. Know what I mean?

Thanks in advance for your help,
Doug Farrell

4.Resource Name Display on Gantt Bars

I have selected to display Resource Names as Gantt Bar 
Text.  However, as my resources are loaded (units) at 85%, 
when the resource name is displayed, the percentage is 
also displayed in brackets next to the resource name (i.e. 
John Doe [85%]).  Is there a way to display the resource 
name w/o the percentage (i.e. John Doe) and maintain the 
85% loading (unit) for the resource?
Thanks.

5.HowDoI hide text under a gantt bar when its rolled up in Project

When I display text under the gantt bar, all of the text gets jumbled when I 
roll up the subtasks.  I want to display the text for the sub task but NOT 
display text in the rolled up gantt bar.  Any ideas?  

6. Gantt Chart Wizard (Critical Path) and Bar Name Corruption

7. Show task name next to Gantt bar?

8. change font for task.name and color of gantt bar based on criteria



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 55 guest