Hide Resource Name on Gantt Bars globally

Microsoft Project

    Sponsored Links

    Next

  • 1. SUmmary tasks do not start when the first child task starts
    My MSP is playing tricks on me. All my summary tasks appear to start at the PROJECT START DATE. Even when the tasks underneath the summary tasks start later, the summary task does not adopt that start date, it stays fixed at the project start date (which makes the daycount wrong). The end date of the summary task adjusts, though. What is going on ? thks
  • 2. Counting Calendar Days
    I am working on a schedule for a construction project that is based on a contract. The contractor has 30 calendar days to complete a portion of the work i.e. from September 15, 2008 to October 15, 2008. When I enter September 15, 2008 into the calendar, the finish day comes up October 24, 2008. should be October 15, 2008. I assume what is going on is the working calendar thing and not including Sat and Sun, How do I get the calendar to count all days for a particular task?
  • 3. Rsource Graphing
    Greetings all. I currently operate MSP 2003 pro desktop version. I support a department that has resources working on 11 different projects. I've set up a labor pool and a master project to view all of the projects and resources. I need to be able to generate a summary level, timescaled graph, that indicates the labor allocation, by resource, for selected resources. The graph preferably needs to be a vertical bar type chart with 100% being the upper threshold so that overallocations and underallocations can be easily observed by the department manager. I can easily generate the resource usage sheet in MSP but the department manager wants to see a graph. He does not want to see a stack of graphs (one for each resource) that MSP generates. I beleive I understand from this forum that it is not possible to generate the type of graph I'm seeking in MSP. Looks as if I'll need to send the data to MS Excel which doesn't look too daunting. However, I'd like to automate as much as possible as this graph will be updated frequently. I'm not VBA conversant but am willing to learn. All input is appreciated.
  • 4. weekend and duration dates conflict
    I am in Sales and I create a "preliminary" Microsoft schedule for my proposal. This schedule is intended to start / end dates and task duration along with required predecessor/successor links. Our company just recently converted to Microsoft Project 2007. For installation of the work, I need to show weekend installation only, for nine consecutive weekends. I created a new calendar called "Weekend Work" and linked the pertinent tasks to this new schedule. My first installation is for 3 days with a start of Saturday and end date of Tuesday. It should have an end date of Monday. My remaining installation tasks have a duration of 2 days with a start of Saturday and an end date of Monday. It should have an end date of Sunday. I tried to force the dates, but it will not reflect the forced change. What am I missing?
  • 5. Filters in Summary Projects
    I have a summary project containing 10 projects all using the same resource pool. I am trying to filter by resource. When I launch the "Resource Using" filter the drop down list of available resources is empty. Does this filter not work in a summary project?

Hide Resource Name on Gantt Bars globally

Postby U3RldmUgVmluY2VudA » Sun, 08 Feb 2009 07:00:03 GMT

Is there a way to hide the Resource Name that is displayed next to each Gantt 
bar? I know you can remove the name display on a bar-by-bar, individual 
basis, but is there a global setting that will "not" show resource names for 
the entire project?

TIA,

Steve

Re: Hide Resource Name on Gantt Bars globally

Postby Mike Glen » Sun, 08 Feb 2009 08:22:56 GMT

Hi Steve,

Welcome to this Microsoft Project newsgroup :)

Try Format/Bar Styles... and in the Text tab, delete the entry for Resource 
Names from the "right" cell.

FAQs, companion products and other useful Project information can be seen at 
this web address:  http://www.**--****.com/ 

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See  http://www.**--****.com/ 







Re: Hide Resource Name on Gantt Bars globally

Postby Rod Gill » Sun, 08 Feb 2009 08:26:17 GMT

Yes. Select Format, Bar Styles and remove Resource Names from critical and 
noncritical bars. Better yet create separate Views for each report you need 
to produce rather than formatting and re-formatting the same View.

-- 

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
 http://www.**--****.com/ 









Similar Threads:

1.Ability to change Gantt Bar color based on Resource Name

Is there a way to customize project to display different color bars in Gantt 
based on the resource classification (name)

2.Task Summary view: Resource names above gantt bar?

How do I get the resource names to show above the bar in the task summary 
gantt chart view? They appear for all the sub-tasks when summary task filter 
is not applied, but not on the sumary task bar. 

I want to print out a task summarygantt chart view, but I need to see all 
the resources that are assigned to a particular task summary (we are a small 
organization, there are no more than 6 resources assigned to any task). The 
resource name column is also blank at the summary level.

I have tried the gantt chart wizard, but nothing happens in the summary view.

Thanks
M


-- 
New to MSP
MS Project 2003

3.Howto change bar color globally for a resource

Hi all,

I'm using MS Project Pro 2002 and want to know if I can do something.
I've got a schedule layed out for a project with resources assigned to
tasks. Is it possible to give a resource (my team members) a
particular bar color so when they look at a project they can
immediately see what tasks are theirs? I can set the bar colors/styles
on a bar by bar basis, but this is a pain. What I'd like is to set a
bar color/style for each resource so when I move resources around, the
bar color/styles follow it. Know what I mean?

Thanks in advance for your help,
Doug Farrell

4.Resource Name Display on Gantt Bars

I have selected to display Resource Names as Gantt Bar 
Text.  However, as my resources are loaded (units) at 85%, 
when the resource name is displayed, the percentage is 
also displayed in brackets next to the resource name (i.e. 
John Doe [85%]).  Is there a way to display the resource 
name w/o the percentage (i.e. John Doe) and maintain the 
85% loading (unit) for the resource?
Thanks.

5.HowDoI hide text under a gantt bar when its rolled up in Project

When I display text under the gantt bar, all of the text gets jumbled when I 
roll up the subtasks.  I want to display the text for the sub task but NOT 
display text in the rolled up gantt bar.  Any ideas?  

6. Gantt Chart Wizard (Critical Path) and Bar Name Corruption

7. Show task name next to Gantt bar?

8. change font for task.name and color of gantt bar based on criteria



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 11 guest