Hide Resource Name on Gantt Bars globally

Microsoft Project

    Sponsored Links

    Next

  • 1. extended deadline marker
    Hi, Is there an option for the deadline red flag to appear after a defined period of time from the deadline? not at the instant the activity has passed its deadline. Thanks, Assaf.
  • 2. Outline Codes - Hierarchical Structure
    I've upgraded from MSP 2003 to 2007, but my outline codes, which are hierarchical (for instance system/subsystems) are not displaying properly. In 2003, I grouped on levels 1 and 2 of the hierarchy and they would display the subordinate codes under the main code, with the code Descriptions as the headings. In 2007 when I try this the main code heading comes up with "No (code value)", and the subordinate heading is a little black rectangle. Grouping under "each value" works better, but again the headings are the code Values rather than the code Descriptions. Two questions then: 1) Can the Outline Code Description be displayed, or is it only the Code Value? 2) Is it possible to get hierarchical codes to work in 2007? I tried setting up dummy codes to see if it was a conversion problem but the same issue arose. I'm trying to avoid having to replace my hierarchy with individual codes
  • 3. imbedding fields in other software
    Is it possible to imbed fields from project in a word file. For example, could I imbed the Author field from the properties table in MSP into a table in word.
  • 4. Working a non-working day
    The project I am working on requires travel on a saturday, and go-live on a Sunday. The only way to force project 2007 to accept this is make the task - Must End on the saturday. This is fine as long as the project does not split in time. How do I do this without imposing this criteria. (Sat and Sun normally a non-working day). Also I have a training course running from tues to Sat (5 days) - must end on Sat on task - but I have to show the task as running as 4 days to make the ghannt chart look correct - as If I leave as 5 days it schedules in the Monday? Help please
  • 5. Discrepency between timephase and task fields
    Hi, I have "several" files were I have noted differences between what is shown in a task field and the sum of the timephased. Is this normal? For instance my Project Level Task Baseline cost = $289,051.16 The timephased sums to = $289,024.47 Although in this case it is only about 26$, I find these discrepencies often enough and I can't explain them. So, in this case I resbaseline... now I have baseline cost of $290,300.17 at the task level, and $290,281.00 timephase (sum). A difference of 19$. So, what is few dollars between friends you say???!!! Is this normal???? In this case I'm using MS Pro 2003 SP3. /Spiro.

Hide Resource Name on Gantt Bars globally

Postby U3RldmUgVmluY2VudA » Sun, 08 Feb 2009 07:00:03 GMT

Is there a way to hide the Resource Name that is displayed next to each Gantt 
bar? I know you can remove the name display on a bar-by-bar, individual 
basis, but is there a global setting that will "not" show resource names for 
the entire project?

TIA,

Steve

Re: Hide Resource Name on Gantt Bars globally

Postby Mike Glen » Sun, 08 Feb 2009 08:22:56 GMT

Hi Steve,

Welcome to this Microsoft Project newsgroup :)

Try Format/Bar Styles... and in the Text tab, delete the entry for Resource 
Names from the "right" cell.

FAQs, companion products and other useful Project information can be seen at 
this web address:  http://www.**--****.com/ 

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See  http://www.**--****.com/ 







Re: Hide Resource Name on Gantt Bars globally

Postby Rod Gill » Sun, 08 Feb 2009 08:26:17 GMT

Yes. Select Format, Bar Styles and remove Resource Names from critical and 
noncritical bars. Better yet create separate Views for each report you need 
to produce rather than formatting and re-formatting the same View.

-- 

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
 http://www.**--****.com/ 









Similar Threads:

1.Ability to change Gantt Bar color based on Resource Name

Is there a way to customize project to display different color bars in Gantt 
based on the resource classification (name)

2.Task Summary view: Resource names above gantt bar?

How do I get the resource names to show above the bar in the task summary 
gantt chart view? They appear for all the sub-tasks when summary task filter 
is not applied, but not on the sumary task bar. 

I want to print out a task summarygantt chart view, but I need to see all 
the resources that are assigned to a particular task summary (we are a small 
organization, there are no more than 6 resources assigned to any task). The 
resource name column is also blank at the summary level.

I have tried the gantt chart wizard, but nothing happens in the summary view.

Thanks
M


-- 
New to MSP
MS Project 2003

3.Howto change bar color globally for a resource

Hi all,

I'm using MS Project Pro 2002 and want to know if I can do something.
I've got a schedule layed out for a project with resources assigned to
tasks. Is it possible to give a resource (my team members) a
particular bar color so when they look at a project they can
immediately see what tasks are theirs? I can set the bar colors/styles
on a bar by bar basis, but this is a pain. What I'd like is to set a
bar color/style for each resource so when I move resources around, the
bar color/styles follow it. Know what I mean?

Thanks in advance for your help,
Doug Farrell

4.Resource Name Display on Gantt Bars

I have selected to display Resource Names as Gantt Bar 
Text.  However, as my resources are loaded (units) at 85%, 
when the resource name is displayed, the percentage is 
also displayed in brackets next to the resource name (i.e. 
John Doe [85%]).  Is there a way to display the resource 
name w/o the percentage (i.e. John Doe) and maintain the 
85% loading (unit) for the resource?
Thanks.

5.HowDoI hide text under a gantt bar when its rolled up in Project

When I display text under the gantt bar, all of the text gets jumbled when I 
roll up the subtasks.  I want to display the text for the sub task but NOT 
display text in the rolled up gantt bar.  Any ideas?  

6. Gantt Chart Wizard (Critical Path) and Bar Name Corruption

7. Show task name next to Gantt bar?

8. change font for task.name and color of gantt bar based on criteria



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 40 guest