Why are task bars red?

Microsoft Project

    Sponsored Links


  • 1. Move macro
    I have a macro in my project file and want to copy this macro to my colleague is there a quick way of doing this in P2000?
  • 2. Help! Trial version expired; cannot see some of my tasks
    How do I restore the missing tasks? The line items are on the project plan, but the text is missing on the "task name" field. Have viewed the plan with a licensed version of Project and still cannot see all of the task names.
  • 3. Auto Calculating Fields
    Hi Guys, After installing a patch for project 2003 to fix the not outdenting issue i am no longer able to auto calculate fields. If i change a value in a row then all the other relevant fields in that row will change, but the changes are not reflected / calculated in the totals for instance. This worked fine before installing any updates, after installing the patch it stopped working, installing the service pack did not help either. Also, when i tell project to calculate the fields manualy it works fine. Thank you for your help Gareth Roberts
  • 4. Resource allocation question: Changing percentage from month to month?
    I have a question about Project that I have been unable to find an answer to (at least in my usenet search): I want to be able to implement my resoure allocation in a project such that if the project lasts for example 2 months, I can have resource X working 70% of his time on that project for the first month and 45% of his time on that project for the second month. Thus far, I can only figure out (a) how to allocate a fixed percentage of someone's time for the duration of the task or (b), have to specify explicit hours through the resource usage view. For example, I'd ideally like to create a task that goes from September 1st to October 31st and then say "from September 1st to September 30th, X is allocated 70% to this project. From October 1st to October 31st, X is allocated 45% to this project". Forgive me if the answer was already out there and I couldn't find it, but any help would be much appreciated. Thanks! Sergio.
  • 5. Duration of using "split task".
    Hello, Would anyone be able to tell me how to modify the duration of a split after I split a task? I have a problem when I split certain tasks. It'll auotmatically split it for 3 days instead of 1 day at a time. This only happens on certains tasks. I've tried to scroll over the remainder of the task bar from the right to shorten the duration but it removes the split. Would it have anything to do with "working days" & "non-working days"? -- Thank you, Michael Anthony

Why are task bars red?

Postby cm9iZXJ0Zg » Mon, 29 Sep 2008 03:26:01 GMT

I just created a project schedule using MS Project 2007 and I also created a 
baseline.   When I do a "View -> Tracking Gantt" I now see the task bars for 
my current schedule on top and baseline task bars just below them.  Why is it 
that some of the top task bars (for the current schedule) are colored red 
while others are colored blue?  I don't understand what this difference in 
color means.


Re: Why are task bars red?

Postby Jan De Messemaeker » Mon, 29 Sep 2008 03:55:44 GMT


Red bars are those on the critical path.
Read FAQ 42 on  http://www.**--****.com/ 

Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:

Similar Threads:

1.Why Am I seeing 2 line items per task

I need help in understanding why all of a sudden each 
task is seen twice, but on the print preview only once. I 
rebooted Windows XP and still see two entries with the 
same line item number for each entry on my project 
scheule. Help!

2.Why am I getting "An error has occured in the script of this page"

whenever I try to see help information within the "assistance" section of the 
MS Project site, I get "An error has occured in the script of this page" 
messages. The result is that I cannot access any of the help information. 

Why is this happening? 

3.Why am I asked to save a file of a different name when closing a f

I have a project that someone else created that I have to edit, call this 
Project1. When I edit Project1 and try to save it, I get the message 'Do you 
want to save changes to Project2'. 
I can't see any links to this project from the Tools menu, is there anywhere 
else I should be looking?


4.why do task bars shorten when adding resources

I have two questions,

Why do task bars shorten when resource names are added to the ends and how 
can I stop this happening?

Also, when I want to extend the duration over which a repeating task occurs, 
the newly added events also appear in new lines beneath the original 
recurring task line. When these erroneous lines are removed, the additional 
repeat tasks also disappear from the row into which they were added. This is 
most annoying and I'd really appreciate some help sorting it out.

 Can someone please help?

5.Why it is giving me 401 Unauthorized Error when i am running i

6. Why am I getting Arguement Value not Valid

7. Why it is giving me 401 Unauthorized Error when i am running it fr

8. Gantt Bars to go RED

Return to Microsoft Project


Who is online

Users browsing this forum: No registered users and 14 guest