Why are task bars red?

Microsoft Project

    Sponsored Links

    Next

  • 1. How do I publish a copy of a project sheet?
    I need to Publish a version of my current project sheet. We'd like to be able to have so it updates automatically like a html page of an excel doc. Any ideas?
  • 2. need help on MS Project Task Timings
    If a task has started at a particular time and this task waits for completion of another task in the middle, how could i show this in the network diagram?
  • 3. help! How to put a duration (days) more than start & finish dates
    I need to put a certain duration, which doesnt match with the start and finish dates, please hlpe me to do this, its very important to my project. Thanks Nairy
  • 4. Cost Roll Up in Project 2003
    I am interested in rolling up column costs in MSP 2003. The COST column automatically rolls sums the sub amounts up. However, if I choose COST2, it does not provide this functionality. What is a way I can roll up $ amounts in other COST columns? THANKS KJ
  • 5. Revised resource max units is not reflected in assignment units.
    We're in the planning process of setting up a project so many values are subject to change per meetings, discussions, etc. I've revised some of my resource max units, but my new value is not reflected in the assigment units. I do revise the max units - in the resource view. The project is quite large, but with few resources so deleting and re-adding the resource really isn't a viable option. ? For the sake of curiosity of revised max units to high and low values just to see if this affects assignment units, i.e., 100%, 150%, 1%, etc., - no change. What am I missing? Any and all appreciated!

Why are task bars red?

Postby cm9iZXJ0Zg » Mon, 29 Sep 2008 03:26:01 GMT

I just created a project schedule using MS Project 2007 and I also created a 
baseline.   When I do a "View -> Tracking Gantt" I now see the task bars for 
my current schedule on top and baseline task bars just below them.  Why is it 
that some of the top task bars (for the current schedule) are colored red 
while others are colored blue?  I don't understand what this difference in 
color means.

Thanks.

Re: Why are task bars red?

Postby Jan De Messemaeker » Mon, 29 Sep 2008 03:55:44 GMT

Hi,

Red bars are those on the critical path.
Read FAQ 42 on  http://www.**--****.com/ 
HTH

-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
 http://www.**--****.com/ 







Similar Threads:

1.Why Am I seeing 2 line items per task

I need help in understanding why all of a sudden each 
task is seen twice, but on the print preview only once. I 
rebooted Windows XP and still see two entries with the 
same line item number for each entry on my project 
scheule. Help!

2.why is duration red in project 2003

why is duration red in project 2003

3.Why am I getting "An error has occured in the script of this page"

whenever I try to see help information within the "assistance" section of the 
MS Project site, I get "An error has occured in the script of this page" 
messages. The result is that I cannot access any of the help information. 

Why is this happening? 

4.Why am I asked to save a file of a different name when closing a f

I have a project that someone else created that I have to edit, call this 
Project1. When I edit Project1 and try to save it, I get the message 'Do you 
want to save changes to Project2'. 
I can't see any links to this project from the Tools menu, is there anywhere 
else I should be looking?

Susan

5.why do task bars shorten when adding resources

I have two questions,

Why do task bars shorten when resource names are added to the ends and how 
can I stop this happening?

Also, when I want to extend the duration over which a repeating task occurs, 
the newly added events also appear in new lines beneath the original 
recurring task line. When these erroneous lines are removed, the additional 
repeat tasks also disappear from the row into which they were added. This is 
most annoying and I'd really appreciate some help sorting it out.

 Can someone please help?

6. Why it is giving me 401 Unauthorized Error when i am running i

7. Why am I getting Arguement Value not Valid

8. Why it is giving me 401 Unauthorized Error when i am running it fr



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 15 guest