Why are task bars red?

Microsoft Project

    Sponsored Links

    Next

  • 1. linking some project information to the other projects
    Hello, I would like to know how to link some of the inofrmation from one project to the other project files using MS project. The reason is that few column entries ( 40% of all the infoamrion from master schedule) could be shared to initiate the other projects by the other users. This will reduce the duplications and increase the efficiencies. I thought we may be able to link few columns infomations to the other project files and therfore the project managers are able initiate their projects by just adding more information to the file. Please advise Majid
  • 2. Earned Value - Export to excel
    I was wondering if anyone has found a good way to export Earned Value to excel? I have tried both the Timescaled Data and export map, but neither method provide the correct data in the excel spreadsheet. Ultimately what I am looking for is a way to export weekly roll ups of earned value for status reporting. If I use the timescaled method, MS project spreads the value over the timeframe of the project I am reporting on. If I use the export map method, MS project provides data for the entire project and it is not rolled up per week. Any help would be greatly appreciated! Thanks! Sarah
  • 3. MS-Project 2000 error in date for september month
    Hi We are using ms-project 2000. I'm working an a resources project files. I wanted to set Monday 06 of september 2004 as a vacation day. Surprise !! The september 2004 calender show Monday 08. I tried to find any bugs related to an error concerning calendar date in Microsoft web site and cannot find any. Any comments to resolves this problem will be appreciate. Thank you
  • 4. How do I set a task out by a specific duration from another?
    Try making Task B the Predecessor of Task A with a Start- Start relationship and a three month negative lag. >-----Original Message----- >I have yet to understand how I link two tasks together where the suceeding >task is driving the predessing one. Task B is independet of Task A and >always comes after Task A. Task A must be 3 months ahead of Task B, but it's >(Task A's) start or finish doesn't effect Task B. When I move Task B, I want >Task A to move automatically. How do I do this painlessly? >. >
  • 5. local resources vs. resource pool
    can a local resource update hours worked through Web Access or do they have to become a resource within the resource pool

Why are task bars red?

Postby cm9iZXJ0Zg » Mon, 29 Sep 2008 03:26:01 GMT

I just created a project schedule using MS Project 2007 and I also created a 
baseline.   When I do a "View -> Tracking Gantt" I now see the task bars for 
my current schedule on top and baseline task bars just below them.  Why is it 
that some of the top task bars (for the current schedule) are colored red 
while others are colored blue?  I don't understand what this difference in 
color means.

Thanks.

Re: Why are task bars red?

Postby Jan De Messemaeker » Mon, 29 Sep 2008 03:55:44 GMT

Hi,

Red bars are those on the critical path.
Read FAQ 42 on  http://www.**--****.com/ 
HTH

-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
 http://www.**--****.com/ 







Similar Threads:

1.Why Am I seeing 2 line items per task

I need help in understanding why all of a sudden each 
task is seen twice, but on the print preview only once. I 
rebooted Windows XP and still see two entries with the 
same line item number for each entry on my project 
scheule. Help!

2.Why am I getting "An error has occured in the script of this page"

whenever I try to see help information within the "assistance" section of the 
MS Project site, I get "An error has occured in the script of this page" 
messages. The result is that I cannot access any of the help information. 

Why is this happening? 

3.Why am I asked to save a file of a different name when closing a f

I have a project that someone else created that I have to edit, call this 
Project1. When I edit Project1 and try to save it, I get the message 'Do you 
want to save changes to Project2'. 
I can't see any links to this project from the Tools menu, is there anywhere 
else I should be looking?

Susan

4.why do task bars shorten when adding resources

I have two questions,

Why do task bars shorten when resource names are added to the ends and how 
can I stop this happening?

Also, when I want to extend the duration over which a repeating task occurs, 
the newly added events also appear in new lines beneath the original 
recurring task line. When these erroneous lines are removed, the additional 
repeat tasks also disappear from the row into which they were added. This is 
most annoying and I'd really appreciate some help sorting it out.

 Can someone please help?

5.Why it is giving me 401 Unauthorized Error when i am running i

6. Why am I getting Arguement Value not Valid

7. Why it is giving me 401 Unauthorized Error when i am running it fr

8. Gantt Bars to go RED



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 96 guest