Why are task bars red?

Microsoft Project

    Sponsored Links

    Next

  • 1. Automatically change Gannt Bar Colour
    Hi, In Project 2003 I use a Shedule Project which incorporates all current projects in minor detail. One column headed "Type" contains a drop down box to select; UK, Europe, Internal etc to define to nature of that project. Each Gannt bar colour is different for each type, ie, Uk is black, Europe is yellow and so on. Currently I have to manually select these colour. If i can, how can i automatically set the colour of the Ganny bar when the type is selected from the drop-down. I'm not vastly over-qualified with Project 2003, so simple answers most appreciated. Thanks.
  • 2. Custom Toolbar/Formatting Macros w/ multiple users
    Hi, I've created a custom toolbar that has 3 macros that format fonts 3 different colors. I've placed the custom toolbar into the project file through organizer (as well as in global.mpt). I've copied the 3 modules to the file as well as leaving them in global.mpt. My problem is that even though I've done that when someone else opens it they have no custom toolbar and when they try to run the macros they get an error "The macros in this project are disabled. Please refer to the online help or documentation of the host application to determine how to enable macros." If I go to their desk and copy the macro from the file to global the macros work... but at no point is the custom toolbar available. If I didn't have 20 people in multiple locations I could just run around and create the toolbar for them but seems to me there should be a way to attach these to the file not just my PC. Thoughts? Thanks! Tara
  • 3. Merging/Extracting Milestones from different project schedules
    Hi, I want to create a MS project file which will have milestones from 5-6 different project schedules merged into one project. Is there a way to do this? Rajula
  • 4. change dates in 1 file to filter to 4 other files
    I maintain 5 project files. I only maintain the start finish dates and the tasks. I am not concerned with % or constraints, etc. Is there a way to change dates and/or tasks in 1 file and have the information filter to the other 4 files so that I do not have to go in to each file and change the information?
  • 5. Interruption in Project Plan
    I have a project that has been interrupted by our customer. This has an unknown duration right now but I would like to reflect in the schedule what the delay will do to our end date. I want to be able to report in our weekly status meetings that project X is now X days behind schedule because we are not currently working on it. What is the best way to be able to do this? I was thinking I should insert a task and then make all of the unfinished tasks successors to it, but then I don't know what to do about already started tasks. Finally how do I reflect that my resources are not working? Thanks for any help,

Why are task bars red?

Postby cm9iZXJ0Zg » Mon, 29 Sep 2008 03:26:01 GMT

I just created a project schedule using MS Project 2007 and I also created a 
baseline.   When I do a "View -> Tracking Gantt" I now see the task bars for 
my current schedule on top and baseline task bars just below them.  Why is it 
that some of the top task bars (for the current schedule) are colored red 
while others are colored blue?  I don't understand what this difference in 
color means.

Thanks.

Re: Why are task bars red?

Postby Jan De Messemaeker » Mon, 29 Sep 2008 03:55:44 GMT

Hi,

Red bars are those on the critical path.
Read FAQ 42 on  http://www.**--****.com/ 
HTH

-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
 http://www.**--****.com/ 







Similar Threads:

1.Why Am I seeing 2 line items per task

I need help in understanding why all of a sudden each 
task is seen twice, but on the print preview only once. I 
rebooted Windows XP and still see two entries with the 
same line item number for each entry on my project 
scheule. Help!

2.Why am I getting "An error has occured in the script of this page"

whenever I try to see help information within the "assistance" section of the 
MS Project site, I get "An error has occured in the script of this page" 
messages. The result is that I cannot access any of the help information. 

Why is this happening? 

3.Why am I asked to save a file of a different name when closing a f

I have a project that someone else created that I have to edit, call this 
Project1. When I edit Project1 and try to save it, I get the message 'Do you 
want to save changes to Project2'. 
I can't see any links to this project from the Tools menu, is there anywhere 
else I should be looking?

Susan

4.why do task bars shorten when adding resources

I have two questions,

Why do task bars shorten when resource names are added to the ends and how 
can I stop this happening?

Also, when I want to extend the duration over which a repeating task occurs, 
the newly added events also appear in new lines beneath the original 
recurring task line. When these erroneous lines are removed, the additional 
repeat tasks also disappear from the row into which they were added. This is 
most annoying and I'd really appreciate some help sorting it out.

 Can someone please help?

5.Why it is giving me 401 Unauthorized Error when i am running i

6. Why am I getting Arguement Value not Valid

7. Why it is giving me 401 Unauthorized Error when i am running it fr

8. Gantt Bars to go RED



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 43 guest