Why are task bars red?

Microsoft Project

    Sponsored Links

    Next

  • 1. Traking time on task
    actual We are tracking the performance to schedule of various contractors based on a few metrics, one utilizing time on task. Once a week I will be meeting with our contractors, and updating actual hours and resources invested on task. I made a practice schedule and entered some actual hours and resources on a task. The task originally had (1) resource at 100% for 3/18 3/20 (3 days). Creating a scenario of being told from the contractor the task actually took 2 days, 2 people; starting on 3/18, and ending on 3/19; I went to enter the information accordingly. I entered 8 hours for each resource on the 18, same for the 19 and entered 3/19 as the actual finish date. Upon entering the 19th as the finish date, the hours for the 19th changed from 8 to 7 for a total duration of 1.88 days. Why? I need to have actual time on tasks records, and cannot afford to have the system changing the actual hours I put in. I did go back and adjust the hours from 7 to 8, but the duration remained 1.88. My calendar is set for 8 hours working (7:00 12:00, 1:00 4:00). None of my tasks are set for effort driven. I understand the eed to adjust ahead of time by adding/removing resources (ie. using effort driven tasks), but what about the back end, when you need to enter actual (work)? Nick
  • 2. Help- Back save 2007 file to 2000 Project
    I have two files written in 2007 that I need someone to save in 2000 format so I can work with the files. Thank you. Bob
  • 3. Overallocation issue (day by day) MSP2003
    I am using MSP2003 and often see an issue in resource usage view where (on a day-by-day basis or even week-by-week) a resource/task is highlighted as overallocated at that level even though it is not. I have read previous posts which explain that MS treats any overallocation against every 60s period and that the recommended fix is to manually edit the working hours on hour-by-hour basis. However is there any way to change the setting such that MSP only flags overallocations on a day-by-day basis (as any smaller time period is not really relevant to me)? It is quite fiddly and time-consuming to manually correct overallocations when they do occur even though I am only really concerned with the day-by-day view. Does MSP2007 offer any solutions in this area compared with '03?
  • 4. work to complete task is fraction of duration per day
    uI am trying to figure out how to disconnect Work from Duration. If I have a task that requires 4 hours of work per day for 5 days, I want Work to be 20 hours and the duration to be 5 days. How do I do that? Thanks in advance for any help.

Why are task bars red?

Postby cm9iZXJ0Zg » Mon, 29 Sep 2008 03:26:01 GMT

I just created a project schedule using MS Project 2007 and I also created a 
baseline.   When I do a "View -> Tracking Gantt" I now see the task bars for 
my current schedule on top and baseline task bars just below them.  Why is it 
that some of the top task bars (for the current schedule) are colored red 
while others are colored blue?  I don't understand what this difference in 
color means.

Thanks.

Re: Why are task bars red?

Postby Jan De Messemaeker » Mon, 29 Sep 2008 03:55:44 GMT

Hi,

Red bars are those on the critical path.
Read FAQ 42 on  http://www.**--****.com/ 
HTH

-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
 http://www.**--****.com/ 







Similar Threads:

1.Why Am I seeing 2 line items per task

I need help in understanding why all of a sudden each 
task is seen twice, but on the print preview only once. I 
rebooted Windows XP and still see two entries with the 
same line item number for each entry on my project 
scheule. Help!

2.Why am I getting "An error has occured in the script of this page"

whenever I try to see help information within the "assistance" section of the 
MS Project site, I get "An error has occured in the script of this page" 
messages. The result is that I cannot access any of the help information. 

Why is this happening? 

3.Why am I asked to save a file of a different name when closing a f

I have a project that someone else created that I have to edit, call this 
Project1. When I edit Project1 and try to save it, I get the message 'Do you 
want to save changes to Project2'. 
I can't see any links to this project from the Tools menu, is there anywhere 
else I should be looking?

Susan

4.why do task bars shorten when adding resources

I have two questions,

Why do task bars shorten when resource names are added to the ends and how 
can I stop this happening?

Also, when I want to extend the duration over which a repeating task occurs, 
the newly added events also appear in new lines beneath the original 
recurring task line. When these erroneous lines are removed, the additional 
repeat tasks also disappear from the row into which they were added. This is 
most annoying and I'd really appreciate some help sorting it out.

 Can someone please help?

5.Why it is giving me 401 Unauthorized Error when i am running i

6. Why am I getting Arguement Value not Valid

7. Why it is giving me 401 Unauthorized Error when i am running it fr

8. Gantt Bars to go RED



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 26 guest