Why are task bars red?

Microsoft Project

    Sponsored Links

    Next

  • 1. task filter
    sI am a shopfloor planner and have a schedule of all taks asoociated within the project, such as label produciton, batch record completion, etc. and my team uses the filter to see the due dates of their job. When recently using the filter function, the tasks shown were only April through Decemnber and all other tasks from January through March were not included. Is there a reason this could be happening? I have also recently updated resource names, but since they filter under the "task" column, I didnt think this could be the reason. Please advise on how to resolve. Thanks!
  • 2. Group By Subtotals
    I am using task usage view and have a group by (say text1) field. It is great, but the work assignments don't subtotal (or total) up to the group field. IE - Text 1 Task Jan Feb Mar 12345 Task A 2.5 2.5 2.5 Task B 2.0 2.0 2.0 23456 Task C 1.5 1.5 1.5 Task D .05 .05 .05
  • 3. Master Project with imbedded subprojects-problem displaying resour
    Have an MS Project 'Master' Plan that includes subprojects imbedded within it. These subprojects comme in by pointing to a separate subproject file. Both the master and the subprojects use the same resource list. Reources are assigned in the subproject tasks and in the higher lever master plan tasks. The % complete is also assigned in subproject tasks. When I bring in the subprojects, the resources and the % complete do not appear, but they are there in the separate subproject file. Can anyone help me identify what I may be doing wrong? -- C L Haddad
  • 4. More column like <% complete>
    Hi, Experts!! I have a BIG question... I want to know if it is possible to add more than one column like <% complete> I have seen several numerical, of date, and of text, but with none of them I achieve that it behaves as that of <% complete> specifically in considering percentages of advance for the macro activities (Automatic calculation) Exist any alternative? Thanks in advance Martin
  • 5. Delay tast cost for 1 month
    Here is an example of what I need to do: I have a task that will take 5 Weeks All my cost are task based not resource based. This task will cost $1000 and it is prorated. I don't want the cost to come out of my budget until I recieve an invoice which I recieve on the 5th of every month. The cost have to be prorated because I get invoiced for % Complete at billing date I am trying to use this for a cash flow report and can't seem to get it right.

Why are task bars red?

Postby cm9iZXJ0Zg » Mon, 29 Sep 2008 03:26:01 GMT

I just created a project schedule using MS Project 2007 and I also created a 
baseline.   When I do a "View -> Tracking Gantt" I now see the task bars for 
my current schedule on top and baseline task bars just below them.  Why is it 
that some of the top task bars (for the current schedule) are colored red 
while others are colored blue?  I don't understand what this difference in 
color means.

Thanks.

Re: Why are task bars red?

Postby Jan De Messemaeker » Mon, 29 Sep 2008 03:55:44 GMT

Hi,

Red bars are those on the critical path.
Read FAQ 42 on  http://www.**--****.com/ 
HTH

-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
 http://www.**--****.com/ 







Similar Threads:

1.Why Am I seeing 2 line items per task

I need help in understanding why all of a sudden each 
task is seen twice, but on the print preview only once. I 
rebooted Windows XP and still see two entries with the 
same line item number for each entry on my project 
scheule. Help!

2.why is duration red in project 2003

why is duration red in project 2003

3.Why am I getting "An error has occured in the script of this page"

whenever I try to see help information within the "assistance" section of the 
MS Project site, I get "An error has occured in the script of this page" 
messages. The result is that I cannot access any of the help information. 

Why is this happening? 

4.Why am I asked to save a file of a different name when closing a f

I have a project that someone else created that I have to edit, call this 
Project1. When I edit Project1 and try to save it, I get the message 'Do you 
want to save changes to Project2'. 
I can't see any links to this project from the Tools menu, is there anywhere 
else I should be looking?

Susan

5.why do task bars shorten when adding resources

I have two questions,

Why do task bars shorten when resource names are added to the ends and how 
can I stop this happening?

Also, when I want to extend the duration over which a repeating task occurs, 
the newly added events also appear in new lines beneath the original 
recurring task line. When these erroneous lines are removed, the additional 
repeat tasks also disappear from the row into which they were added. This is 
most annoying and I'd really appreciate some help sorting it out.

 Can someone please help?

6. Why it is giving me 401 Unauthorized Error when i am running i

7. Why am I getting Arguement Value not Valid

8. Why it is giving me 401 Unauthorized Error when i am running it fr



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 38 guest