Why are task bars red?

Microsoft Project

    Sponsored Links

    Next

  • 1. Resource Usage View not showing Actual Work or AWP
    This is in a Project Server 2003 environment. The time-phased portion of the Resource Usage view will display 'Work' and 'Cum. Work", and other fields, but will not display 'Act. Work' , Actual Work Protected or 'Base. Work' when they are added to the Details list. What am I doing wrong?
  • 2. Non-Working Time
    I have a project that has a 1-day start in February then doesn't start again until mid-March. I would like to be able to produce the schedule showing daily without showing all the non-working time.
  • 3. Gantt Chart start date setting
    How do I have a Gantt Chart (the one that shows up in the right hand pane) begin with a date that I set? Right now it always starts from the current date. Thanks, -- CJH
  • 4. Timescale analysis
    Project 2007 has removed the timescale data analysis feature and resorts to Visual Reports for the same type of analysis. I was able to use timescale analysis to generate %complete "forecasts", but can't find a Visual Report setup that will include % complete, so I can't forecast and use the data to make useful charts in excel. -- RRickard
  • 5. Feedback about using Project to model Agile iterations
    I am considering the use of Project to model time boxed Agile Iterations. One of the challenges to this is that Agile is very team oriented. The team has reponsibility for completing several user stories (use-cases) in each iteration. Rigorously, I suppose this is equal to a single bucket task, modeling all the work done on the iteration, and a series of milestones, one for each user story, dependent on the bucket task. At the end of the iteration, either the user storeies were completed and tested -- or not. If they were completed, the milestore is set to 100% complete. If not, the milestone/user story is moved to the next iteration. Any Ideas? Any first hand experience? HOW Would Project Server 2007 help with this??? Can I assign resources to summary tasks in 2007 ???

Why are task bars red?

Postby cm9iZXJ0Zg » Mon, 29 Sep 2008 03:26:01 GMT

I just created a project schedule using MS Project 2007 and I also created a 
baseline.   When I do a "View -> Tracking Gantt" I now see the task bars for 
my current schedule on top and baseline task bars just below them.  Why is it 
that some of the top task bars (for the current schedule) are colored red 
while others are colored blue?  I don't understand what this difference in 
color means.

Thanks.

Re: Why are task bars red?

Postby Jan De Messemaeker » Mon, 29 Sep 2008 03:55:44 GMT

Hi,

Red bars are those on the critical path.
Read FAQ 42 on  http://www.**--****.com/ 
HTH

-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
 http://www.**--****.com/ 







Similar Threads:

1.Why Am I seeing 2 line items per task

I need help in understanding why all of a sudden each 
task is seen twice, but on the print preview only once. I 
rebooted Windows XP and still see two entries with the 
same line item number for each entry on my project 
scheule. Help!

2.Why am I getting "An error has occured in the script of this page"

whenever I try to see help information within the "assistance" section of the 
MS Project site, I get "An error has occured in the script of this page" 
messages. The result is that I cannot access any of the help information. 

Why is this happening? 

3.Why am I asked to save a file of a different name when closing a f

I have a project that someone else created that I have to edit, call this 
Project1. When I edit Project1 and try to save it, I get the message 'Do you 
want to save changes to Project2'. 
I can't see any links to this project from the Tools menu, is there anywhere 
else I should be looking?

Susan

4.why do task bars shorten when adding resources

I have two questions,

Why do task bars shorten when resource names are added to the ends and how 
can I stop this happening?

Also, when I want to extend the duration over which a repeating task occurs, 
the newly added events also appear in new lines beneath the original 
recurring task line. When these erroneous lines are removed, the additional 
repeat tasks also disappear from the row into which they were added. This is 
most annoying and I'd really appreciate some help sorting it out.

 Can someone please help?

5.Why it is giving me 401 Unauthorized Error when i am running i

6. Why am I getting Arguement Value not Valid

7. Why it is giving me 401 Unauthorized Error when i am running it fr

8. Gantt Bars to go RED



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 19 guest