Why are task bars red?

Microsoft Project

    Sponsored Links

    Next

  • 1. changing the password for a protected file
    Hi I have Project 2002 (yes, very old...). I saved my file w/ pw protection using Save As and then Options. It works fine - but now I need to change the password to a differnt word so others can access it. If I repeat the same process (using Save As) it just keeps the old password. I want to "edit" the actual password or assign a new one. Can you help? Thanks, MaryS
  • 2. Start / Finish Date Calculation Erros
    I am using MS Proj Prof 2003. My Project Administrator is using MS Prof Prof 2000. When he sends me a copy of the Proj file (*.mpp), the file I open on my computer sporadically has different start/finish dates and durations from the one on his computer. If I send the file on my computer back to him, he sees the correct data when he opens the file. I have checked all the variables, such as project calendar, and the are the same in both project files. Any ideas as to what could be causing this issue. Thanks!
  • 3. subtotals of a date range.
    Hi Project Experts, I want to complete an analysis in which the amount of work on tasks in a given daterange is calculated. When I apply the daterange filter, the tasks from 1-jan-07 till 31-dec-07 are filtered correctly. However the subtotals on the summary tasks show the amount of work for the complete daterange of the projects! e.g. Summary Task 110h work task 1 60h work start 1-oct-06 finish 1-dec-06 task 2 10h work start 1-feb-07 finish 1-apr-07 task 3 40h work start 1-may-07 finish 1-jul-07 When I apply the daterange filter for tasks in 2007, the summary task still shows an amount of 110h work, where 50h was wanted, because task1 in the example was completed in 2006. Does anyone know how to solve this problem? Best regards, Henk
  • 4. Completed Task report
    When I run the completed task report setting the period to "Week" it groups the tasks by their start date. How do I change it so that it groups the tasks by the week they finished. I am using Project 2003 Standard
  • 5. Timesheet Compliance
    do anyone knows how to calculate timesheet compliance using .mpp

Why are task bars red?

Postby cm9iZXJ0Zg » Mon, 29 Sep 2008 03:26:01 GMT

I just created a project schedule using MS Project 2007 and I also created a 
baseline.   When I do a "View -> Tracking Gantt" I now see the task bars for 
my current schedule on top and baseline task bars just below them.  Why is it 
that some of the top task bars (for the current schedule) are colored red 
while others are colored blue?  I don't understand what this difference in 
color means.

Thanks.

Re: Why are task bars red?

Postby Jan De Messemaeker » Mon, 29 Sep 2008 03:55:44 GMT

Hi,

Red bars are those on the critical path.
Read FAQ 42 on  http://www.**--****.com/ 
HTH

-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
 http://www.**--****.com/ 







Similar Threads:

1.Why Am I seeing 2 line items per task

I need help in understanding why all of a sudden each 
task is seen twice, but on the print preview only once. I 
rebooted Windows XP and still see two entries with the 
same line item number for each entry on my project 
scheule. Help!

2.why is duration red in project 2003

why is duration red in project 2003

3.Why am I getting "An error has occured in the script of this page"

whenever I try to see help information within the "assistance" section of the 
MS Project site, I get "An error has occured in the script of this page" 
messages. The result is that I cannot access any of the help information. 

Why is this happening? 

4.Why am I asked to save a file of a different name when closing a f

I have a project that someone else created that I have to edit, call this 
Project1. When I edit Project1 and try to save it, I get the message 'Do you 
want to save changes to Project2'. 
I can't see any links to this project from the Tools menu, is there anywhere 
else I should be looking?

Susan

5.why do task bars shorten when adding resources

I have two questions,

Why do task bars shorten when resource names are added to the ends and how 
can I stop this happening?

Also, when I want to extend the duration over which a repeating task occurs, 
the newly added events also appear in new lines beneath the original 
recurring task line. When these erroneous lines are removed, the additional 
repeat tasks also disappear from the row into which they were added. This is 
most annoying and I'd really appreciate some help sorting it out.

 Can someone please help?

6. Why it is giving me 401 Unauthorized Error when i am running i

7. Why am I getting Arguement Value not Valid

8. Why it is giving me 401 Unauthorized Error when i am running it fr



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 0 guest