Why are task bars red?

Microsoft Project

    Sponsored Links

    Next

  • 1. Variable work rates
    John can dig a hole twice as fast as Pete. I would like Project 2000 to determine either John or Pete to work on a task "Dig the hole" but that allocation to be made with the goal of minimizing overall project duration. For instance, I would always prefer Joh to dig as he works twice as fast, however, he has other tasks to do that are on the critical path so I get Pete to do the digging that isn't on the critical path and so finish the project as quickly as possible. Can I do that?
  • 2. summry task and subtask progress
    how summry task progress can be delinked from subtask. i know that we can stop progressing summary task by tool-option-manual but then i cannot update sumarry tsak even maually. please very urgent for me thanks yousaf
  • 3. Assign a weight to a project task
    When defining tasks within a plan, some tasks carry more importance than others. You could have 10 tasks where 3 of the tasks truly represent 75% of the work that needs to get done. Is there any way to define this within MSProject? Thanks
  • 4. Assignment Dates not changing
    One of our PMs came to me saying that she changed the dates on a task but the resource wasn't getting the change in assignment. I investigated and found this: The task is a Fixed Duration task. The duration was originally set at 7 days and work was set at 40 horus. One resource was assigned. Everything worked fine. The PM increased the duration to 73 days to give the resource more time to finish it (the work remained the same). The task is now showing the new finish date, however, when I looked at the assignment information it still had the original date. The work contour indicator had somehow gotten set to "countour" (I'm sure the PM didn't set it so I'm not sure how it happened). I was able to set the new finish date manually (and then had to reset the work) and everything is now looking good. I have not been able to find any information on this problem nor have I been able to recreate it. Any ideas would be helpful. Thanks, -- ...Cindy
  • 5. work contour - contoured / flat?
    I accidentally posted this to the Project Server thread first... My project schedule is fixed duration and not effort driven. I've noticed for a while that some tasks have a very high (2,000%...3,000%) units for resources assigned to the task. I think I stumbled across the cause of the high units. I was looking at the Task Usage view and noticed that many of the resource assignments for tasks had a work contour of contoured instead of flat. Upon further research the task start and finish was different for these tasks than start and finish in the assignment information. I suspect that the assignment originally had start of 9/7 and finish of 9/14...I assigned a resource....then I changed the finish of the assignment to 9/21....but the assignment information for the resource assigned to the task still shows the finish date as 9/14??? I have never noticed this before. Can someone tell me what I'm doing that is causing a different in start/finish for the task and for the assignment? What should I be doing to avoid this and keep the work contour flat unless I specifically change it? -- Thanks, Jesse -- Jesse

Why are task bars red?

Postby cm9iZXJ0Zg » Mon, 29 Sep 2008 03:26:01 GMT

I just created a project schedule using MS Project 2007 and I also created a 
baseline.   When I do a "View -> Tracking Gantt" I now see the task bars for 
my current schedule on top and baseline task bars just below them.  Why is it 
that some of the top task bars (for the current schedule) are colored red 
while others are colored blue?  I don't understand what this difference in 
color means.

Thanks.

Re: Why are task bars red?

Postby Jan De Messemaeker » Mon, 29 Sep 2008 03:55:44 GMT

Hi,

Red bars are those on the critical path.
Read FAQ 42 on  http://www.**--****.com/ 
HTH

-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
 http://www.**--****.com/ 







Similar Threads:

1.Why Am I seeing 2 line items per task

I need help in understanding why all of a sudden each 
task is seen twice, but on the print preview only once. I 
rebooted Windows XP and still see two entries with the 
same line item number for each entry on my project 
scheule. Help!

2.why is duration red in project 2003

why is duration red in project 2003

3.Why am I getting "An error has occured in the script of this page"

whenever I try to see help information within the "assistance" section of the 
MS Project site, I get "An error has occured in the script of this page" 
messages. The result is that I cannot access any of the help information. 

Why is this happening? 

4.Why am I asked to save a file of a different name when closing a f

I have a project that someone else created that I have to edit, call this 
Project1. When I edit Project1 and try to save it, I get the message 'Do you 
want to save changes to Project2'. 
I can't see any links to this project from the Tools menu, is there anywhere 
else I should be looking?

Susan

5.why do task bars shorten when adding resources

I have two questions,

Why do task bars shorten when resource names are added to the ends and how 
can I stop this happening?

Also, when I want to extend the duration over which a repeating task occurs, 
the newly added events also appear in new lines beneath the original 
recurring task line. When these erroneous lines are removed, the additional 
repeat tasks also disappear from the row into which they were added. This is 
most annoying and I'd really appreciate some help sorting it out.

 Can someone please help?

6. Why it is giving me 401 Unauthorized Error when i am running i

7. Why am I getting Arguement Value not Valid

8. Why it is giving me 401 Unauthorized Error when i am running it fr



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 75 guest