Can't Renumber WBS for "Selected Tasks"

Microsoft Project

    Sponsored Links

    Next

  • 1. Project crash, can't open affected file
    I have been working on creating a project file. I ran into an ODBC error when trying to save the file at some point, could be a memory issue on my machine, maybe I lost connection to the server momentarily, who knows. Now I cannot open the affected file even after manually checking it in via web access. The file appears to open, prompts me that I have a circular reference in the file (oops! typo on my part), then tries to open the rest of the way and crashes Project with that "I'm sorry..." error message. The file becomes checked out under that account and I can't try to open it again until I manually check it in via Web Access again. Anyone have any idea what I can do to recover this file? I saved it directly to the server (since Project defaults that way) so I don't have any .mpp file anywhere to work on. Can I get at the database and fix the circular reference there? Some tips would be appreciated. Seems odd that the circular reference would cause such a dramatic crash, seeing as how Project provides a circular reference toolbar, but what else could be going on? Thanks in advance! Karen
  • 2. Unable to view Admin userlists in Project Server after install
    Hi, You need to install SQL server before any project server installation. see psread10.htm for details. This file can be found under the computer the project server is installed Hope this helps >-----Original Message----- >After initial install of Project Server, it does not >present any of the grid boxes to view user accounts or >security data. It just presents "loading data" and hangs. >This is under the Admin menu while logged on as >Administrator. > >I have uninstalled IIS and project server and reinstalled >with no success. > > >. >
  • 3. MS Project 2002 Tutorial Error
    What is "MSO_Large" passed to HH_GET_WIN_TYPE has not been specified? Got the error on Tutorial. Cheers...
  • 4. Security - Different Enterprise Resource views
    Is it possible to setup security to allow a project manager see the entire Enterprise Resource Pool through MS Project Professional when building the team but only see their resources (based on RBS) when using the Resource Center on PWA ? I've found that depending upon the set-up in the categories I can get either the ability for them to see their resources or all resources. Any assistance would be appreciated. Thanks, Bill
  • 5. Thanks for your responses so far
    Thanks to you both Kevin and Dale for your responses. I have forwarded the info to the PM. Hopefully somewhere it there he will get some joy :-) Thanks again, John

Can't Renumber WBS for "Selected Tasks"

Postby J Baird » Sat, 06 Mar 2004 04:22:47 GMT

I have a schedule, where I've renumbered the WBS numbers for selected tasks,
on a regular basis.  ([Project][Wbs][Renumber][Select Tasks])

All of a sudden, in the [WBS Renumber] dialog box, the [Selected Tasks]
option is greyed out (the [Entire Project] option is still selectable).
Nothing else has changed...the WBS settings and Code Definition are still
the same as when the [Selected Tasks] option was available.

To try to fix the problem , I selected [Project][Wbs][Renumber][Entire
Project], to renumber the entire project, hoping that would bring back the
[Selected Tasks] option, but it didn't.

I can't find anything in the knowledge base about this.  Has anyone seen
this behavior before, and if so, do you know what caused it?



Re: Can't Renumber WBS for "Selected Tasks"

Postby Gard Ducouret » Sat, 06 Mar 2004 06:19:08 GMT

Hello J.

If you select only one row, the [WBS Renumber] dialog box presents only the
[Entire Project] option.
Have you tried to select several rows ?

Gard Ducouret



"J Baird" <jill[dot]baird[at]lmco[dot]com> a rit dans le message de


tasks,



Re: Can't Renumber WBS for "Selected Tasks"

Postby J Baird » Sat, 06 Mar 2004 06:56:12 GMT

Of course...As I said, I've renumbered selected tasks on a regular basis.
Now, the [Selected Tasks] option is greyed out.  I know that I'm not the
only person that this has happened to.





the

still
the



Similar Threads:

1.Renumber WBS for Selected Tasks is broken for one file (it used to work)

I have a schedule where I've frequently renumbered the WBS values for parts
of the schedule, using the [Project][Wbs][Renumber][Select Tasks] command.

All of a sudden, when I select several tasks (not just one!), and click the
[WBS Renumber] dialog box, the [Selected Tasks] option is greyed out (the
[Entire Project] option is still selectable).

Nothing else has changed...the WBS settings and Code Definition are still
the same as when the [Selected Tasks] option was available.  When MSP
renumbers the WBS for "Selected Tasks", it uses the first selected item as a
starting reference, and there's a valid WBS value in that task.  The numbers
it would normally create with this command, are not already in the Project
file, so uniqueness isn't a problem.

To try to fix the problem , I selected [Project][Wbs][Renumber][Entire
Project], to renumber the entire project, hoping that would bring back the
[Selected Tasks] option, but it didn't.

I can't find anything in the knowledge base about this.  I've had several
users complain of the same problem, but not until they have renumbered
selected tasks, a lot of times.

Has anyone seen this behavior before, and if so, do you know how we can get
the Selected Tasks WBS Renumbering to work again?





2.Renumbering WBS using the Project/WBS pull down window

I have MS Project 2003 Standard: I wish to renumber an existing WBS. The Help 
instructions say: Select Project, then WBS, then Renumber, then Entire 
project.  When I select Project, then WBS,the window is locked in the "Define 
Code" mode.  The Renumber option is muted and cannot be selected. Icannot 
proceed.
What am I doing wrong?
How can I renumber an existing WBS?

3.WBS Renumber greyed out

Hi,

I'd like to renumber my WBS elements.  When I click Projects, WBS the 
renumber menu is in grey and can not be used.  This happens even a new 
project with only two tasks.  Any help would be greatly appreciated.

Thanks,

  Darrell

4.Renumber WBS

hello,
i created a wbs code.  however, after deleting and moving tasks, the code is 
no longer correct.  in microsoft help, i found that you can renumber the wbs 
code for the entire project.
but if i go in a task sheet view and i go to the project menu, wbs, i cannot 
select renumber?
how can i solve this problem ? (i have a feeling this is an easy one...)
thank you.
andy

5.How to renumber W.B.S. codes

I have MS Project 2003 Professional.  There is an option on the Project menu 
for 'W.B.S.'  'Renumber', but the 'Renumber' function is not highlighted and 
won't let me select it.  According to online help you should be able to 
select your tasks by name (or entire project) and renumber the W.B.S. codes 
but I cannot get it to work.  How can you do this?

6. Renumbering the WBS

7. Ability to renumber WBS not consistent between views.

8. WBS Cannot Renumber



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 40 guest