Can't Renumber WBS for "Selected Tasks"

Microsoft Project

    Sponsored Links

    Next

  • 1. Project Server 2003 / sharepoint team services Site Template
    Does anyone have experience creating a new site template? If so... of the sharepoint modules within project server (issues, risks, documents, portal site) which modules does the template effect. The documentation on this area is very limited Bill
  • 2. PWA 2003 "Print Grid" size limit. Pretty please answer this if you
    Pretty pretty please with sugar on top answer this if you can. I've looked at the documentation, I've searched the groups and Microsofts knowledgebase. I can't find anything. Thanks!
  • 3. Error creating subweb with STS
    Hi, I'm having a problem with creating a sub web. On one particular project, I get and error message "Error occurred when creating subweb. Subweb does not seem to exist". I then partially makes the subweb folder under the wwwroot folder, but it's not registering. I then manually delete the subweb folder and try again. Same results. I have also entered in the path to the incomplete subweb and delete it in the Manage subwebs page. What do I need to do to create the clean subweb? If I edit the subweb address and open it, the page displays "The list or view of a list that is referenced here no longer exists. The list or view of a list that is referenced here no longer exists." Steve
  • 4. Difference In Remaining Work
    I have a difference between remaining work displaying in MS Project and the amount of remaining work when queried directly from the database. This difference is apparent in only a few records. MS Project displays the correct information in "Task Usage" view. Detailed Information: Due to MS Projects poor reporting, we use Crystal Reports to identify overdue tasks. Using MS's suggested SQL Statement I have identified 4 overdue tasks. However, viewing those tasks in "Usage View" the "Remaining Work" column has 0. Application Information: Project 2002 Pro & Server SQL Statement used: --select-- PROJ_NAME as Project, TASK_NAME as Task, RES_NAME as Resource, ASSN_WORK/60000 as Work_Assigned, (ASSN_WORK/60000 - ASSN_REM_WORK/60000) as Work_Complete, ASSN_REM_WORK/60000 as Work_Remaining, ASSN_FINISH_DATE as Scheduled_Finish from MSP_WEB_PROJECTS p, MSP_WEB_ASSIGNMENTS a, MSP_WEB_RESOURCES r where a.ASSN_REM_WORK > 0 and DATEDIFF(day, a.ASSN_FINISH_DATE, @check_date) > @days_late and a.WPROJ_ID = p.WPROJ_ID and a.WRES_ID = r.WRES_ID

Can't Renumber WBS for "Selected Tasks"

Postby J Baird » Sat, 06 Mar 2004 04:22:47 GMT

I have a schedule, where I've renumbered the WBS numbers for selected tasks,
on a regular basis.  ([Project][Wbs][Renumber][Select Tasks])

All of a sudden, in the [WBS Renumber] dialog box, the [Selected Tasks]
option is greyed out (the [Entire Project] option is still selectable).
Nothing else has changed...the WBS settings and Code Definition are still
the same as when the [Selected Tasks] option was available.

To try to fix the problem , I selected [Project][Wbs][Renumber][Entire
Project], to renumber the entire project, hoping that would bring back the
[Selected Tasks] option, but it didn't.

I can't find anything in the knowledge base about this.  Has anyone seen
this behavior before, and if so, do you know what caused it?



Re: Can't Renumber WBS for "Selected Tasks"

Postby Gard Ducouret » Sat, 06 Mar 2004 06:19:08 GMT

Hello J.

If you select only one row, the [WBS Renumber] dialog box presents only the
[Entire Project] option.
Have you tried to select several rows ?

Gard Ducouret



"J Baird" <jill[dot]baird[at]lmco[dot]com> a rit dans le message de


tasks,



Re: Can't Renumber WBS for "Selected Tasks"

Postby J Baird » Sat, 06 Mar 2004 06:56:12 GMT

Of course...As I said, I've renumbered selected tasks on a regular basis.
Now, the [Selected Tasks] option is greyed out.  I know that I'm not the
only person that this has happened to.





the

still
the



Similar Threads:

1.Renumber WBS for Selected Tasks is broken for one file (it used to work)

I have a schedule where I've frequently renumbered the WBS values for parts
of the schedule, using the [Project][Wbs][Renumber][Select Tasks] command.

All of a sudden, when I select several tasks (not just one!), and click the
[WBS Renumber] dialog box, the [Selected Tasks] option is greyed out (the
[Entire Project] option is still selectable).

Nothing else has changed...the WBS settings and Code Definition are still
the same as when the [Selected Tasks] option was available.  When MSP
renumbers the WBS for "Selected Tasks", it uses the first selected item as a
starting reference, and there's a valid WBS value in that task.  The numbers
it would normally create with this command, are not already in the Project
file, so uniqueness isn't a problem.

To try to fix the problem , I selected [Project][Wbs][Renumber][Entire
Project], to renumber the entire project, hoping that would bring back the
[Selected Tasks] option, but it didn't.

I can't find anything in the knowledge base about this.  I've had several
users complain of the same problem, but not until they have renumbered
selected tasks, a lot of times.

Has anyone seen this behavior before, and if so, do you know how we can get
the Selected Tasks WBS Renumbering to work again?





2.Renumbering WBS using the Project/WBS pull down window

I have MS Project 2003 Standard: I wish to renumber an existing WBS. The Help 
instructions say: Select Project, then WBS, then Renumber, then Entire 
project.  When I select Project, then WBS,the window is locked in the "Define 
Code" mode.  The Renumber option is muted and cannot be selected. Icannot 
proceed.
What am I doing wrong?
How can I renumber an existing WBS?

3.WBS Renumber greyed out

Hi,

I'd like to renumber my WBS elements.  When I click Projects, WBS the 
renumber menu is in grey and can not be used.  This happens even a new 
project with only two tasks.  Any help would be greatly appreciated.

Thanks,

  Darrell

4.Renumber WBS

hello,
i created a wbs code.  however, after deleting and moving tasks, the code is 
no longer correct.  in microsoft help, i found that you can renumber the wbs 
code for the entire project.
but if i go in a task sheet view and i go to the project menu, wbs, i cannot 
select renumber?
how can i solve this problem ? (i have a feeling this is an easy one...)
thank you.
andy

5.How to renumber W.B.S. codes

I have MS Project 2003 Professional.  There is an option on the Project menu 
for 'W.B.S.'  'Renumber', but the 'Renumber' function is not highlighted and 
won't let me select it.  According to online help you should be able to 
select your tasks by name (or entire project) and renumber the W.B.S. codes 
but I cannot get it to work.  How can you do this?

6. Renumbering the WBS

7. Ability to renumber WBS not consistent between views.

8. WBS Cannot Renumber



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 63 guest