Can't Renumber WBS for "Selected Tasks"

Microsoft Project

    Sponsored Links

    Next

  • 1. Portfolio Analyzer Question
    I am just starting to build my Portfolio Analyzer view and the fields that I would like to plot in my view are" By Project name Baseline Work Actual Work Percent complete The Pivot Table automatically contains the Project name, Baseline Work, and Actual Work fields, but Percent complete is not include. How do I get some of the fields like Percent complete, Baseline Start/Finish, Actual Start/Finish that resides in the database for every project to appear in the PivotTable field list? My goal is to create Portfolio Analyzer views to display project metric trends. This means that I would need some of the other fields that resides in a project schedule to appear in the PivotTable Field list when I create my charts.
  • 2. Exporting
    Hi, Does anyone know a way to export a consolidated cashflow report to excel? I am in need to create a pie graphe with such information. Thanks
  • 3. Project Manager - Authentication
    Set up a Project Server account with the same permissions you are trying to set up and you can test it that way. >-----Original Message----- >Hello ALL, >I am working in a Test Environment with MSP Server 2002. >Ques: In PWA, can we restrict the PMs to view only the >projects they have uploaded. How does it work? I mean is >it that tho the PM can see other projects he cannot check >out those projects unless/untill its the project he >uploaded to server. I am using Windows Authentication so >I cannot login in as anybody else to verify this. >Help will be appreciated. >Thank you, >DV. >. >
  • 4. Setting up admin tasks in project server2002 environment
    Having some trouble setting up admin tasks, which I would like to use for ongoing overhead activities (using MSProject server2002). (a summary of this is described in the MS white paper 'Timesheet Improvements in Microsoft Office Project Server 2003') Having set the task as 12 month fixed duration, non-effort driven, which other task settings would apply? The problem is when resources are assigned the duration changes. Also, if zero work is entered, as recommended in the white paper, any amount of time entered in web access forces the %completion to be 100%.

Can't Renumber WBS for "Selected Tasks"

Postby J Baird » Sat, 06 Mar 2004 04:22:47 GMT

I have a schedule, where I've renumbered the WBS numbers for selected tasks,
on a regular basis.  ([Project][Wbs][Renumber][Select Tasks])

All of a sudden, in the [WBS Renumber] dialog box, the [Selected Tasks]
option is greyed out (the [Entire Project] option is still selectable).
Nothing else has changed...the WBS settings and Code Definition are still
the same as when the [Selected Tasks] option was available.

To try to fix the problem , I selected [Project][Wbs][Renumber][Entire
Project], to renumber the entire project, hoping that would bring back the
[Selected Tasks] option, but it didn't.

I can't find anything in the knowledge base about this.  Has anyone seen
this behavior before, and if so, do you know what caused it?



Re: Can't Renumber WBS for "Selected Tasks"

Postby Gard Ducouret » Sat, 06 Mar 2004 06:19:08 GMT

Hello J.

If you select only one row, the [WBS Renumber] dialog box presents only the
[Entire Project] option.
Have you tried to select several rows ?

Gard Ducouret



"J Baird" <jill[dot]baird[at]lmco[dot]com> a rit dans le message de


tasks,



Re: Can't Renumber WBS for "Selected Tasks"

Postby J Baird » Sat, 06 Mar 2004 06:56:12 GMT

Of course...As I said, I've renumbered selected tasks on a regular basis.
Now, the [Selected Tasks] option is greyed out.  I know that I'm not the
only person that this has happened to.





the

still
the



Similar Threads:

1.Renumber WBS for Selected Tasks is broken for one file (it used to work)

I have a schedule where I've frequently renumbered the WBS values for parts
of the schedule, using the [Project][Wbs][Renumber][Select Tasks] command.

All of a sudden, when I select several tasks (not just one!), and click the
[WBS Renumber] dialog box, the [Selected Tasks] option is greyed out (the
[Entire Project] option is still selectable).

Nothing else has changed...the WBS settings and Code Definition are still
the same as when the [Selected Tasks] option was available.  When MSP
renumbers the WBS for "Selected Tasks", it uses the first selected item as a
starting reference, and there's a valid WBS value in that task.  The numbers
it would normally create with this command, are not already in the Project
file, so uniqueness isn't a problem.

To try to fix the problem , I selected [Project][Wbs][Renumber][Entire
Project], to renumber the entire project, hoping that would bring back the
[Selected Tasks] option, but it didn't.

I can't find anything in the knowledge base about this.  I've had several
users complain of the same problem, but not until they have renumbered
selected tasks, a lot of times.

Has anyone seen this behavior before, and if so, do you know how we can get
the Selected Tasks WBS Renumbering to work again?





2.Renumbering WBS using the Project/WBS pull down window

I have MS Project 2003 Standard: I wish to renumber an existing WBS. The Help 
instructions say: Select Project, then WBS, then Renumber, then Entire 
project.  When I select Project, then WBS,the window is locked in the "Define 
Code" mode.  The Renumber option is muted and cannot be selected. Icannot 
proceed.
What am I doing wrong?
How can I renumber an existing WBS?

3.WBS Renumber greyed out

Hi,

I'd like to renumber my WBS elements.  When I click Projects, WBS the 
renumber menu is in grey and can not be used.  This happens even a new 
project with only two tasks.  Any help would be greatly appreciated.

Thanks,

  Darrell

4.Renumber WBS

hello,
i created a wbs code.  however, after deleting and moving tasks, the code is 
no longer correct.  in microsoft help, i found that you can renumber the wbs 
code for the entire project.
but if i go in a task sheet view and i go to the project menu, wbs, i cannot 
select renumber?
how can i solve this problem ? (i have a feeling this is an easy one...)
thank you.
andy

5.How to renumber W.B.S. codes

I have MS Project 2003 Professional.  There is an option on the Project menu 
for 'W.B.S.'  'Renumber', but the 'Renumber' function is not highlighted and 
won't let me select it.  According to online help you should be able to 
select your tasks by name (or entire project) and renumber the W.B.S. codes 
but I cannot get it to work.  How can you do this?

6. Renumbering the WBS

7. Ability to renumber WBS not consistent between views.

8. WBS Cannot Renumber



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 31 guest