Can't Renumber WBS for "Selected Tasks"

Microsoft Project

    Sponsored Links

    Next

  • 1. MS PWA Actuals & Remaining Work / Reporting
    Using MS Project Server 2003 we require team members to report actuals (hrs worked) per day AND remaining work (hrs) left for the task. Is there anyway to do so? I only see 3 options for forcing managers to comply and that is not an option. Also we require team members to report to a manager who will then approve/reject updates then get updated in the plan. Overall project manager (1 person) will review and republish then print variance reports against baseline values. Any advice on how to configure? Any advice on how to hide columns from PWA to restrict team members what they see? Thanks
  • 2. Print Issues from Project Server and IE
    I have aprolem with our current installation of Project Server that will not allow any user including administrator to print from the porject server through IE. Only by selecting Print~Preview and then using he Print buton are they able to print the document, and it is printing with the left hand pane, also cutting off the right hand side. If we put an item in Edit mode, File~Print doesn't work. We must select File~Print Preview and then it will print. After File~Print, we are intermittently able to select File~Print on the same item and have the item print properly. If we select another item, we revert back to having to use Print~Preview again. Using Project Server 2002 on Win2003 server. HP Printers, and yes, have tried everycombination of printer and driver imaginable. Has anyone run across a similar problem or have any ideas. Greatly appreciate any help youmay be able to provide. Michael Hardes ISM Canada
  • 3. ProjectServer 2003 SSO
    All, Does any know of or have implemented an SSO solution using Oblix or RSA that would work with ProjectServer? The research I have done has resulted in very little information regarding SSO with ProjectServer. I was hoping that someone else might have trudged down this path and has some insight. Jason
  • 4. Head Count reports out of Project Server
    Dear all, is there a possibility to get a head count report e.g. 12 PL with skill Java developer are planned within the next six months, out of the OLAP Cube? I would be very glad if you could help me. Greetings

Can't Renumber WBS for "Selected Tasks"

Postby J Baird » Sat, 06 Mar 2004 04:22:47 GMT

I have a schedule, where I've renumbered the WBS numbers for selected tasks,
on a regular basis.  ([Project][Wbs][Renumber][Select Tasks])

All of a sudden, in the [WBS Renumber] dialog box, the [Selected Tasks]
option is greyed out (the [Entire Project] option is still selectable).
Nothing else has changed...the WBS settings and Code Definition are still
the same as when the [Selected Tasks] option was available.

To try to fix the problem , I selected [Project][Wbs][Renumber][Entire
Project], to renumber the entire project, hoping that would bring back the
[Selected Tasks] option, but it didn't.

I can't find anything in the knowledge base about this.  Has anyone seen
this behavior before, and if so, do you know what caused it?



Re: Can't Renumber WBS for "Selected Tasks"

Postby Gard Ducouret » Sat, 06 Mar 2004 06:19:08 GMT

Hello J.

If you select only one row, the [WBS Renumber] dialog box presents only the
[Entire Project] option.
Have you tried to select several rows ?

Gard Ducouret



"J Baird" <jill[dot]baird[at]lmco[dot]com> a rit dans le message de


tasks,



Re: Can't Renumber WBS for "Selected Tasks"

Postby J Baird » Sat, 06 Mar 2004 06:56:12 GMT

Of course...As I said, I've renumbered selected tasks on a regular basis.
Now, the [Selected Tasks] option is greyed out.  I know that I'm not the
only person that this has happened to.





the

still
the



Similar Threads:

1.Renumber WBS for Selected Tasks is broken for one file (it used to work)

I have a schedule where I've frequently renumbered the WBS values for parts
of the schedule, using the [Project][Wbs][Renumber][Select Tasks] command.

All of a sudden, when I select several tasks (not just one!), and click the
[WBS Renumber] dialog box, the [Selected Tasks] option is greyed out (the
[Entire Project] option is still selectable).

Nothing else has changed...the WBS settings and Code Definition are still
the same as when the [Selected Tasks] option was available.  When MSP
renumbers the WBS for "Selected Tasks", it uses the first selected item as a
starting reference, and there's a valid WBS value in that task.  The numbers
it would normally create with this command, are not already in the Project
file, so uniqueness isn't a problem.

To try to fix the problem , I selected [Project][Wbs][Renumber][Entire
Project], to renumber the entire project, hoping that would bring back the
[Selected Tasks] option, but it didn't.

I can't find anything in the knowledge base about this.  I've had several
users complain of the same problem, but not until they have renumbered
selected tasks, a lot of times.

Has anyone seen this behavior before, and if so, do you know how we can get
the Selected Tasks WBS Renumbering to work again?





2.Renumbering WBS using the Project/WBS pull down window

I have MS Project 2003 Standard: I wish to renumber an existing WBS. The Help 
instructions say: Select Project, then WBS, then Renumber, then Entire 
project.  When I select Project, then WBS,the window is locked in the "Define 
Code" mode.  The Renumber option is muted and cannot be selected. Icannot 
proceed.
What am I doing wrong?
How can I renumber an existing WBS?

3.WBS Renumber greyed out

Hi,

I'd like to renumber my WBS elements.  When I click Projects, WBS the 
renumber menu is in grey and can not be used.  This happens even a new 
project with only two tasks.  Any help would be greatly appreciated.

Thanks,

  Darrell

4.Renumber WBS

hello,
i created a wbs code.  however, after deleting and moving tasks, the code is 
no longer correct.  in microsoft help, i found that you can renumber the wbs 
code for the entire project.
but if i go in a task sheet view and i go to the project menu, wbs, i cannot 
select renumber?
how can i solve this problem ? (i have a feeling this is an easy one...)
thank you.
andy

5.How to renumber W.B.S. codes

I have MS Project 2003 Professional.  There is an option on the Project menu 
for 'W.B.S.'  'Renumber', but the 'Renumber' function is not highlighted and 
won't let me select it.  According to online help you should be able to 
select your tasks by name (or entire project) and renumber the W.B.S. codes 
but I cannot get it to work.  How can you do this?

6. Renumbering the WBS

7. Ability to renumber WBS not consistent between views.

8. WBS Cannot Renumber



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 78 guest