predecessors and successors

Microsoft Project

    Sponsored Links

    Next

  • 1. Problem installing Project 2002 on Windows XP Professional
    Hi, I'm facing the problem of "corrupt cabinet" while installing Microsoft Project 2002 on Windows XP. Actually this problem should not be there on XP becoz the Windows Installer is already the new one. I was not able to find any update/patch for Windows Installer for XP. The READMe says that this problem occurs on Windows NT, 98 and 2000 and requires the update to windows installer. That update on the CD doesn't work for XP. It throws error saying something related to Build Version of OS, which is obviously different from NT and 2000. Pls. help. Thanks, Jeremy Smith
  • 2. Unhiding columns in MS Project 2002
    Can anyone provide the proceedure how to unhide a column after it has been hidden? Thanks Mark Woloszyk DaimlerChrysler
  • 3. Microsoft Project 95
    I have updated to windows 2000, am use to microsoft project for windows 95, do I have to upgrade an what should I upgrade to. I use for small projects.
  • 4. 405 Error
    Just thought I'd share the solution in case anyone else runs into this--the MSADC was a red herring--the solution was to change ProjectServer Properties execute permissions to scripts and executables. Hope this helps someone.
  • 5. Multiple Links is Moving My Project Time Up
    I need to apply multiple links to a project that I am working on. Each time I do this, my project extends out at least an additional month. What constraints do I need to do? Anything else? Thanks in advance. Sherree.

predecessors and successors

Postby Ingrid » Wed, 30 Jul 2003 15:57:53 GMT

I am using 4 project files linked to each other in a master
file.  The predecessors and successors don't seem to have
any pattern for when they appear and when they don't.  Eg.
a task in one project(project A) may have three successors
in another one (project B), yet only two show up in project
A in the task list of a gantt chart.  


I've tried turning the "show external sucessors" on and off
in Tools>Options but this doesn't actually hide them all or
show them all - I still get some showing and some not
showing.  

Any ideas how to get some consistency with these?

Thanks, 
Ingrid


Re: predecessors and successors

Postby Jack D. » Thu, 31 Jul 2003 04:39:08 GMT



I think that if all the subprojects are expanded then you will see the
linkages.
But other than that, I find that they are somewhat capricious.

-- 
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check  http://www.**--****.com/ 

-Jack Dahlgren, Project MVP


+++++++++++++++++++



Similar Threads:

1.Two links from predecessor to successor

Please help urgently,im using microsoft project on construction project,i 
need to link two task by using two links SS and FF ,I have tried but i get 
error

Regards,


Lulanga

2.External Predecessors and Successors

I have many External Predecessors and Successors within my schedules.
When looking at Tools, Options, View - Cross project linking options for 
'project name' some of the link show and some do not! It seems not to be 
consistent which ones it omits and which ones it doesn't.

Has anyone seen (or not seen) this before?

Does anyone have a remedy?

Cheers,

Russ.

3.Display Predecessor and Successor Task Names

I want to display for each task row any predecessor and successor task names 
that the task has.
I want to do this because the procject is relatively large.
I think I should use a customized text field. However, I am unsure how to 
code the formula to pull the task name.
Any advice would be appreciated.
Thanks

4.synching predecessor and successor dates based on F-S link

Hi folks,

I'm working with MSP2003 and PS2003.  I have a project with afew tasks that have predecessor - successor relationships.  They are F-S.  Some have a lag, some have a lead time, some have neither.  The issue I have is that when the finish date changes for a predecessor task, the start date for the successor remains unchanged.  I've checked the calculation settings and it is set to recalculate automatically.

For example

Task 115 is a predecessor for task 117.  T115's end date is June 28.  T117's start date is June 30.  If I change T115's end date to July 7, the startdate for T117 remains set to June 30.

Thanks for any insights.

Jim

5.Project: Self Modify the Predecessor and Successor Windows

6. Project: Jump to a predecessor or successor by double clicking it

7. Importing from Ecxel, using WBS predecessor/WBS successor

8. Wrapping Predecessor or Successor Field



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 73 guest