predecessors and successors

Microsoft Project

    Sponsored Links

    Next

  • 1. Filtering complete activites on timesheets
    Unfortunately we are not ready to roll out PWA so we need to use manual timesheets at present (modified Resource Usage view). I would really like to filter completed activities from the timesheet but as far as I can tell there is no way to differentiate between activities which really are finished (ie zero estimates left) and activites which are not actually finished but need to be re-estimated. Can someone help?
  • 2. Table Field Name Creation
    I have created tables for accepting Excel data to create mpp files. The format of the received files tends to change without notice, and I would like to check the format before undertaking the conversion process. Can I create a xcel file by fieldname from the table/s I have created? What I want is essentially to be able to check the data definition of the received file against my table. I can't seem to be able to copy the field name to do so.
  • 3. MS Project 2003
    I have Winnt 4.0 pc's.I bought MS project 2003.I have installed MS Project 2002 on different Winnt 4.0 pc's.I would like to know if I can install Project 2002(Standard) using the MS Project 2003 license.
  • 4. Synchronization problem
    Hello: During syncronization of Sharepoint service with Project Server under risk and issues option in PWA, it gives the following error message i.e. "Projec Server failed to update the links in Project Server Database. Please try again later or contact your administrator" Although i am getting this error message but it works ok and saves whatever i want in risks and issues. I am curious its happening and if happening then internall things are working fine. Very confusing!!!! Please advise me. -KON
  • 5. Project Server2003 admin lockout
    Hi An admin we work with has just locked out\deleted all the project server admins from the webconsole.Is there a SQL table I can update with new admin creds?We're using windows authentication and the Database is on a different server from the front end Regards, Jason

predecessors and successors

Postby Ingrid » Wed, 30 Jul 2003 15:57:53 GMT

I am using 4 project files linked to each other in a master
file.  The predecessors and successors don't seem to have
any pattern for when they appear and when they don't.  Eg.
a task in one project(project A) may have three successors
in another one (project B), yet only two show up in project
A in the task list of a gantt chart.  


I've tried turning the "show external sucessors" on and off
in Tools>Options but this doesn't actually hide them all or
show them all - I still get some showing and some not
showing.  

Any ideas how to get some consistency with these?

Thanks, 
Ingrid


Re: predecessors and successors

Postby Jack D. » Thu, 31 Jul 2003 04:39:08 GMT



I think that if all the subprojects are expanded then you will see the
linkages.
But other than that, I find that they are somewhat capricious.

-- 
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check  http://www.**--****.com/ 

-Jack Dahlgren, Project MVP


+++++++++++++++++++



Similar Threads:

1.Two links from predecessor to successor

Please help urgently,im using microsoft project on construction project,i 
need to link two task by using two links SS and FF ,I have tried but i get 
error

Regards,


Lulanga

2.External Predecessors and Successors

I have many External Predecessors and Successors within my schedules.
When looking at Tools, Options, View - Cross project linking options for 
'project name' some of the link show and some do not! It seems not to be 
consistent which ones it omits and which ones it doesn't.

Has anyone seen (or not seen) this before?

Does anyone have a remedy?

Cheers,

Russ.

3.Display Predecessor and Successor Task Names

I want to display for each task row any predecessor and successor task names 
that the task has.
I want to do this because the procject is relatively large.
I think I should use a customized text field. However, I am unsure how to 
code the formula to pull the task name.
Any advice would be appreciated.
Thanks

4.synching predecessor and successor dates based on F-S link

Hi folks,

I'm working with MSP2003 and PS2003.  I have a project with afew tasks that have predecessor - successor relationships.  They are F-S.  Some have a lag, some have a lead time, some have neither.  The issue I have is that when the finish date changes for a predecessor task, the start date for the successor remains unchanged.  I've checked the calculation settings and it is set to recalculate automatically.

For example

Task 115 is a predecessor for task 117.  T115's end date is June 28.  T117's start date is June 30.  If I change T115's end date to July 7, the startdate for T117 remains set to June 30.

Thanks for any insights.

Jim

5.Project: Self Modify the Predecessor and Successor Windows

6. Project: Jump to a predecessor or successor by double clicking it

7. Importing from Ecxel, using WBS predecessor/WBS successor

8. How to Audit Predecessor and Successor Relationships in Project Pl



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 32 guest