predecessors and successors

Microsoft Project

    Sponsored Links

    Next

  • 1. MSP2002Std - Corrupt mpp's? or just a task linking prob?
    I'm having a problem with task linking. i have an issue where two tasks are linked (FS with no lag time). The second task does not get updated when the first task changes. The second task has the task constraint "ASAP". No resources are assigned and all %complete is zero. The calculation setting for the mpp is "automatic". In one instance of removing the link (in the effort of re- linking them), the start date of the first task moved to 1/1/1984, even though the project start date is 1/1/2003. This is part of a large mpp, but the tasks i am referring to have no other predecessors/successors. They are part of a larger summary task, though, which has no predecessors/successors. Other subtasks are not affected. In fact, even the summary task bar does not show the effect of the other two tasks (it's not stretched out from 1984 to 2003). It just resides over the unaffected subtasks - hence my possible conclusion of a corrupted mpp file. Are there repair possibilities for mpp files or is there another avenue of debugging that i'm missing? Any help would be greatly appreciated. Scott
  • 2. trial version
    I loaded a trial version of project 2002 and have been trying it. Since that time we've purchased a site license for project 2002. How do I go about registering the trial version? Do I have to completely remove the trial version and reinstall the new full version obtained by the license? Thank you, Keith

predecessors and successors

Postby Ingrid » Wed, 30 Jul 2003 15:57:53 GMT

I am using 4 project files linked to each other in a master
file.  The predecessors and successors don't seem to have
any pattern for when they appear and when they don't.  Eg.
a task in one project(project A) may have three successors
in another one (project B), yet only two show up in project
A in the task list of a gantt chart.  


I've tried turning the "show external sucessors" on and off
in Tools>Options but this doesn't actually hide them all or
show them all - I still get some showing and some not
showing.  

Any ideas how to get some consistency with these?

Thanks, 
Ingrid


Re: predecessors and successors

Postby Jack D. » Thu, 31 Jul 2003 04:39:08 GMT



I think that if all the subprojects are expanded then you will see the
linkages.
But other than that, I find that they are somewhat capricious.

-- 
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check  http://www.**--****.com/ 

-Jack Dahlgren, Project MVP


+++++++++++++++++++



Similar Threads:

1.Two links from predecessor to successor

Please help urgently,im using microsoft project on construction project,i 
need to link two task by using two links SS and FF ,I have tried but i get 
error

Regards,


Lulanga

2.External Predecessors and Successors

I have many External Predecessors and Successors within my schedules.
When looking at Tools, Options, View - Cross project linking options for 
'project name' some of the link show and some do not! It seems not to be 
consistent which ones it omits and which ones it doesn't.

Has anyone seen (or not seen) this before?

Does anyone have a remedy?

Cheers,

Russ.

3.Display Predecessor and Successor Task Names

I want to display for each task row any predecessor and successor task names 
that the task has.
I want to do this because the procject is relatively large.
I think I should use a customized text field. However, I am unsure how to 
code the formula to pull the task name.
Any advice would be appreciated.
Thanks

4.synching predecessor and successor dates based on F-S link

Hi folks,

I'm working with MSP2003 and PS2003.  I have a project with afew tasks that have predecessor - successor relationships.  They are F-S.  Some have a lag, some have a lead time, some have neither.  The issue I have is that when the finish date changes for a predecessor task, the start date for the successor remains unchanged.  I've checked the calculation settings and it is set to recalculate automatically.

For example

Task 115 is a predecessor for task 117.  T115's end date is June 28.  T117's start date is June 30.  If I change T115's end date to July 7, the startdate for T117 remains set to June 30.

Thanks for any insights.

Jim

5.Project: Self Modify the Predecessor and Successor Windows

6. Project: Jump to a predecessor or successor by double clicking it

7. Importing from Ecxel, using WBS predecessor/WBS successor

8. How to Audit Predecessor and Successor Relationships in Project Pl



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 20 guest