predecessors and successors

Microsoft Project

    Sponsored Links

    Next

  • 1. Filter the deliverables by date
    At present, I have deliverables that can be filtered by this week, next week, this month and so on. Would that be possible to set up the filter that uses from the current calender date. For example if today is Feb 28 and I filter by "this month" I would like to see all deliverables for one month starting today not just the deliverables for the remining of the month which is Feb. 28 in this case. I hope there is a solution to this. Regards, Majid
  • 2. Published Project no Longer Opens
    Hi, I have a published project that I can no longer open from Project Professional 2003. When I try to open it from the PWA server, I get: "The file "<> \File Name.published" cannot be opened." I can see that the path in MSP_PROJECTS is correct and when I try to open it, I can see that the system is trying to check the file out. Any ideas out there? Thanks in advance, Brad
  • 3. Help Needed in Projectserver 2003
    Hi, Error: The following files have blocked by administrator: /projectserver/LGNINT.ASP. Unable to get login screen. What could be the possible reason in Single machine scenario with sub domain configuration live server on internet. Sandeep
  • 4. Document Libraries and Permissions
    We are experiencing some permission issues with some of our end users and access to our document libraries. Project Server is set up for access using Windows login. It is prompting them for Windows username and password when the click on the 'Document Library' link. And entering their Windows UID/PWD does not work. If a different Windows UID/PWD is entered when prompted (e.g. a domain admin login), then Project Server allows access to the document library and we can view documents. We tried making the users 'Administrators' and grant explicit global Admin permissions via Project Admin tools, and they still could not gain access to the document libraries. These are regular domain users in standard Windows groups. As a test, we added one or two users to the domain admin group, then they can get in w/o problems (obviously we don't want to do that!) - but we were looking for the source of the problem - is it AD or Project Server? Let me know if more information or clarification is needed. Thanks. -- Joe Baker
  • 5. automatic % complete update on open file
    Hello Dear, Would that be possible the presentage complete for all tasks be updated soon the file is opened? I have searched through VBA codes and I was not able to match one or write one Please advise Regards, Majid

predecessors and successors

Postby Ingrid » Wed, 30 Jul 2003 15:57:53 GMT

I am using 4 project files linked to each other in a master
file.  The predecessors and successors don't seem to have
any pattern for when they appear and when they don't.  Eg.
a task in one project(project A) may have three successors
in another one (project B), yet only two show up in project
A in the task list of a gantt chart.  


I've tried turning the "show external sucessors" on and off
in Tools>Options but this doesn't actually hide them all or
show them all - I still get some showing and some not
showing.  

Any ideas how to get some consistency with these?

Thanks, 
Ingrid


Re: predecessors and successors

Postby Jack D. » Thu, 31 Jul 2003 04:39:08 GMT



I think that if all the subprojects are expanded then you will see the
linkages.
But other than that, I find that they are somewhat capricious.

-- 
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check  http://www.**--****.com/ 

-Jack Dahlgren, Project MVP


+++++++++++++++++++



Similar Threads:

1.Two links from predecessor to successor

Please help urgently,im using microsoft project on construction project,i 
need to link two task by using two links SS and FF ,I have tried but i get 
error

Regards,


Lulanga

2.External Predecessors and Successors

I have many External Predecessors and Successors within my schedules.
When looking at Tools, Options, View - Cross project linking options for 
'project name' some of the link show and some do not! It seems not to be 
consistent which ones it omits and which ones it doesn't.

Has anyone seen (or not seen) this before?

Does anyone have a remedy?

Cheers,

Russ.

3.Display Predecessor and Successor Task Names

I want to display for each task row any predecessor and successor task names 
that the task has.
I want to do this because the procject is relatively large.
I think I should use a customized text field. However, I am unsure how to 
code the formula to pull the task name.
Any advice would be appreciated.
Thanks

4.synching predecessor and successor dates based on F-S link

Hi folks,

I'm working with MSP2003 and PS2003.  I have a project with afew tasks that have predecessor - successor relationships.  They are F-S.  Some have a lag, some have a lead time, some have neither.  The issue I have is that when the finish date changes for a predecessor task, the start date for the successor remains unchanged.  I've checked the calculation settings and it is set to recalculate automatically.

For example

Task 115 is a predecessor for task 117.  T115's end date is June 28.  T117's start date is June 30.  If I change T115's end date to July 7, the startdate for T117 remains set to June 30.

Thanks for any insights.

Jim

5.Project: Self Modify the Predecessor and Successor Windows

6. Project: Jump to a predecessor or successor by double clicking it

7. Importing from Ecxel, using WBS predecessor/WBS successor

8. Wrapping Predecessor or Successor Field



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 59 guest