predecessors and successors

Microsoft Project

    Sponsored Links

    Next

  • 1. Column 'confirmed' in resource sheet view
    What is it mean when a resource is marked Yes or No in this column in Resource Sheet View? Please tell me why should I change value in this column. I tried link on Microsoft support site but it did not give me details. Thanks.
  • 2. How to resolve phantom task links
    I continue to be plagued by this issue in our Enterprise environment. We are running Project Pro and Server 2003. When revising task durations/work I have often come across a popup message which states that a constraint upon another task is affected. This would suggest that the task being revised is somehow linked to the task which is referred to in the message. After careful review I find that neither task acts as a predecessor or successor to the other. I cannot seem to find any relation between the two tasks. I have checked the properties dialogue for both tasks and don't know where else to look or how to further diagnose/troubleshoot. Does anyone have ideas about how to handle this???
  • 3. MS Project Ver4
    Don't laugh, but I have damaged disk 4 in the set and if anyone can help with an image or the missing files on this disk you will receive many thanks for keeping he past alive. Stoyev...
  • 4. Create Next Milestone Task Field
    Hello all, I am currently trying to create an enterprise outline code to show the next Milestone for a given Project. I would like to have this show in PWA across many projects (85+). Any insight into how to do this would be appreciated. BIGGER PICTURE: I am trying to create a dashboard for all this projects using the EPM solution and Sharepoint Web Parts as the impl. If anyone has any thoughts on this I am all ears as well. Thanks, Andy

predecessors and successors

Postby Ingrid » Wed, 30 Jul 2003 15:57:53 GMT

I am using 4 project files linked to each other in a master
file.  The predecessors and successors don't seem to have
any pattern for when they appear and when they don't.  Eg.
a task in one project(project A) may have three successors
in another one (project B), yet only two show up in project
A in the task list of a gantt chart.  


I've tried turning the "show external sucessors" on and off
in Tools>Options but this doesn't actually hide them all or
show them all - I still get some showing and some not
showing.  

Any ideas how to get some consistency with these?

Thanks, 
Ingrid


Re: predecessors and successors

Postby Jack D. » Thu, 31 Jul 2003 04:39:08 GMT



I think that if all the subprojects are expanded then you will see the
linkages.
But other than that, I find that they are somewhat capricious.

-- 
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check  http://www.**--****.com/ 

-Jack Dahlgren, Project MVP


+++++++++++++++++++



Similar Threads:

1.Two links from predecessor to successor

Please help urgently,im using microsoft project on construction project,i 
need to link two task by using two links SS and FF ,I have tried but i get 
error

Regards,


Lulanga

2.External Predecessors and Successors

I have many External Predecessors and Successors within my schedules.
When looking at Tools, Options, View - Cross project linking options for 
'project name' some of the link show and some do not! It seems not to be 
consistent which ones it omits and which ones it doesn't.

Has anyone seen (or not seen) this before?

Does anyone have a remedy?

Cheers,

Russ.

3.Display Predecessor and Successor Task Names

I want to display for each task row any predecessor and successor task names 
that the task has.
I want to do this because the procject is relatively large.
I think I should use a customized text field. However, I am unsure how to 
code the formula to pull the task name.
Any advice would be appreciated.
Thanks

4.synching predecessor and successor dates based on F-S link

Hi folks,

I'm working with MSP2003 and PS2003.  I have a project with afew tasks that have predecessor - successor relationships.  They are F-S.  Some have a lag, some have a lead time, some have neither.  The issue I have is that when the finish date changes for a predecessor task, the start date for the successor remains unchanged.  I've checked the calculation settings and it is set to recalculate automatically.

For example

Task 115 is a predecessor for task 117.  T115's end date is June 28.  T117's start date is June 30.  If I change T115's end date to July 7, the startdate for T117 remains set to June 30.

Thanks for any insights.

Jim

5.Project: Self Modify the Predecessor and Successor Windows

6. Project: Jump to a predecessor or successor by double clicking it

7. Importing from Ecxel, using WBS predecessor/WBS successor

8. Wrapping Predecessor or Successor Field



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 19 guest