predecessors and successors

Microsoft Project

    Sponsored Links

    Next

  • 1. Project Resources not appearing
    How do I make my Project Resources for a MS Project appear on the MS Project Server website? I thought if your Project had resources they would appear on the Resource page on the website automatically.
  • 2. How to update project data in project 2002 server?
    Gordon -- I would recommend the following process for updating project data: 1. Open Microsoft Project 2002 2. Open the project containing tasks to be updated 3. Click View - Gantt Chart, if necessary 4. Click View - Table - Tracking 5. Pull the vertical split bar to the right so that you can see the Actual Start, Actual Finish, and % Complete columns 6. Enter these values, as needed, for any task that needs to be updated 7. Save the project Hope this helps. -- Dale A. Howard Project Management Trainer/Consultant Denver, CO "Gordon" < XXXX@XXXXX.COM > wrote in message news:043101c360b0$775ba070$ XXXX@XXXXX.COM ... > Dear Sir: > > How to update project data in project 2002 server? > > For example, if I have to update the date/percentage of > one task, How to do that? Should I update the SQL database > directly? or call PDS to update data. > > Best regards, > Gordon
  • 3. Web Enabled Schedule Integration & Analysis
    I need a scheduling application that allows me to create dependencies between activitie in different projects and then perform critical path analysis of both schedules together and produce reports showing the impact of the new dependencies. Can I do that with Microsoft Project Server or Project Central? Thanks, Mike
  • 4. cannot use project
    I have installed Project 2002. When I open the application, the new project is blank, every view I click on shows a shite page with no cells. When I attempt to open project files they are blank. I have re-installed several times with no luck. Help!
  • 5. Integration of multiple project files
    Hello, I am trying to compile multiple project files into one single project file with the original dates intact, so that the dates integrate themselves with other project dates. Any clue on how I can go about this?

predecessors and successors

Postby Ingrid » Wed, 30 Jul 2003 15:57:53 GMT

I am using 4 project files linked to each other in a master
file.  The predecessors and successors don't seem to have
any pattern for when they appear and when they don't.  Eg.
a task in one project(project A) may have three successors
in another one (project B), yet only two show up in project
A in the task list of a gantt chart.  


I've tried turning the "show external sucessors" on and off
in Tools>Options but this doesn't actually hide them all or
show them all - I still get some showing and some not
showing.  

Any ideas how to get some consistency with these?

Thanks, 
Ingrid


Re: predecessors and successors

Postby Jack D. » Thu, 31 Jul 2003 04:39:08 GMT



I think that if all the subprojects are expanded then you will see the
linkages.
But other than that, I find that they are somewhat capricious.

-- 
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check  http://www.**--****.com/ 

-Jack Dahlgren, Project MVP


+++++++++++++++++++



Similar Threads:

1.Two links from predecessor to successor

Please help urgently,im using microsoft project on construction project,i 
need to link two task by using two links SS and FF ,I have tried but i get 
error

Regards,


Lulanga

2.External Predecessors and Successors

I have many External Predecessors and Successors within my schedules.
When looking at Tools, Options, View - Cross project linking options for 
'project name' some of the link show and some do not! It seems not to be 
consistent which ones it omits and which ones it doesn't.

Has anyone seen (or not seen) this before?

Does anyone have a remedy?

Cheers,

Russ.

3.Display Predecessor and Successor Task Names

I want to display for each task row any predecessor and successor task names 
that the task has.
I want to do this because the procject is relatively large.
I think I should use a customized text field. However, I am unsure how to 
code the formula to pull the task name.
Any advice would be appreciated.
Thanks

4.synching predecessor and successor dates based on F-S link

Hi folks,

I'm working with MSP2003 and PS2003.  I have a project with afew tasks that have predecessor - successor relationships.  They are F-S.  Some have a lag, some have a lead time, some have neither.  The issue I have is that when the finish date changes for a predecessor task, the start date for the successor remains unchanged.  I've checked the calculation settings and it is set to recalculate automatically.

For example

Task 115 is a predecessor for task 117.  T115's end date is June 28.  T117's start date is June 30.  If I change T115's end date to July 7, the startdate for T117 remains set to June 30.

Thanks for any insights.

Jim

5.Project: Self Modify the Predecessor and Successor Windows

6. Project: Jump to a predecessor or successor by double clicking it

7. Importing from Ecxel, using WBS predecessor/WBS successor

8. Wrapping Predecessor or Successor Field



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 68 guest