predecessors and successors

Microsoft Project

    Sponsored Links

    Next

  • 1. VERY SLOW: Opening and Saving Projects on ProjectServer
    Hi Our projectserver is painfully slow: A simple project with one task!!! and no resources defined takes 1min42sec to Save and 52 Sec to open anyone had similar problems ? Config: PSRV2002; Ms Project Pro 2002, SQL Server over 6.5 thanks /Attila
  • 2. Project 2002 crashes after clean install
    Project 2002 Standard crashes after clean install. Windows XP SP1, Dell Dimension 4550 with 1.5 GB of RAM, 2.4Ghz P4. Not the media, can install using same key and same media on a different Machine running XP SP1. Project installs with no errors; upon startup, crashses and wants to send MS and error report. Not file related; crashes whether you are trying to launch with a file, or just open the app. PC also has Office 2000 Professional. ANy ideas would be appreciated. Thanks John Watson jwatson AT imago DOT com (remove the NOSPAM in my email to reply directly to me)
  • 3. MS Project 2002 cannot open the file
    Error message when trying to open an MS Project 2002 file Cannot open the file, check that the file name and path are correct, check that the file format is recognized by Project. Microsoft Project files saved in a version earlier than 98 can't be opened. There are these sympotoms in an article in the knowledge base, however none of the scenarios apply. The file was created with MS Project 2002, fairly recently within a couple of weeks, no macros or VB scripts were used. Can create other documents save and re-open. Does the "fix" apply for this as well!!? Help! Anyone else with this situation with Project!? I have many users using this version and no problems thus far.
  • 4. Project 2002 - EditCopy caused project to close
    I have both Project 2000 and 2002 Standard (new) installed. I have a project with multiple projects inserted (Links are retained). These incerted projects are saved in both 2000 and 98 depending on provider of the project plan. I have created views using special fields. When I try to select all, edit copy in 2002, I receive the error "MS Project has encountered a problem and must close" I even tried saving all plans in 2002 with no help. If I open the plan using 2000, everthing works fine. Any ideas would be appreciated. I know of 2 others with the same problem with the same mpp file that only have 2002 installed.
  • 5. Email Collaboration
    Our company has been attempting, unsuccessfully, to set up email collaboration using Project 2002 Standard and Groupwise 6. We are considering moving over to Project Server, but I would like to know whether email collaboration with Groupwise 6 is likely to work with the server version and if it is necessary to have a CAL for each email user, even if they only provide updates via email.

predecessors and successors

Postby Ingrid » Wed, 30 Jul 2003 15:57:53 GMT

I am using 4 project files linked to each other in a master
file.  The predecessors and successors don't seem to have
any pattern for when they appear and when they don't.  Eg.
a task in one project(project A) may have three successors
in another one (project B), yet only two show up in project
A in the task list of a gantt chart.  


I've tried turning the "show external sucessors" on and off
in Tools>Options but this doesn't actually hide them all or
show them all - I still get some showing and some not
showing.  

Any ideas how to get some consistency with these?

Thanks, 
Ingrid


Re: predecessors and successors

Postby Jack D. » Thu, 31 Jul 2003 04:39:08 GMT



I think that if all the subprojects are expanded then you will see the
linkages.
But other than that, I find that they are somewhat capricious.

-- 
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check  http://www.**--****.com/ 

-Jack Dahlgren, Project MVP


+++++++++++++++++++



Similar Threads:

1.Two links from predecessor to successor

Please help urgently,im using microsoft project on construction project,i 
need to link two task by using two links SS and FF ,I have tried but i get 
error

Regards,


Lulanga

2.External Predecessors and Successors

I have many External Predecessors and Successors within my schedules.
When looking at Tools, Options, View - Cross project linking options for 
'project name' some of the link show and some do not! It seems not to be 
consistent which ones it omits and which ones it doesn't.

Has anyone seen (or not seen) this before?

Does anyone have a remedy?

Cheers,

Russ.

3.Display Predecessor and Successor Task Names

I want to display for each task row any predecessor and successor task names 
that the task has.
I want to do this because the procject is relatively large.
I think I should use a customized text field. However, I am unsure how to 
code the formula to pull the task name.
Any advice would be appreciated.
Thanks

4.synching predecessor and successor dates based on F-S link

Hi folks,

I'm working with MSP2003 and PS2003.  I have a project with afew tasks that have predecessor - successor relationships.  They are F-S.  Some have a lag, some have a lead time, some have neither.  The issue I have is that when the finish date changes for a predecessor task, the start date for the successor remains unchanged.  I've checked the calculation settings and it is set to recalculate automatically.

For example

Task 115 is a predecessor for task 117.  T115's end date is June 28.  T117's start date is June 30.  If I change T115's end date to July 7, the startdate for T117 remains set to June 30.

Thanks for any insights.

Jim

5.Project: Self Modify the Predecessor and Successor Windows

6. Project: Jump to a predecessor or successor by double clicking it

7. Importing from Ecxel, using WBS predecessor/WBS successor

8. Wrapping Predecessor or Successor Field



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 65 guest