predecessors and successors

Microsoft Project

    Sponsored Links

    Next

  • 1. Editing Formula for Actual Cost
    Hi, I want to edit the formula for Actual Cost field in Microsoft Project 2003. Is it possible to do so??? Also, I wish to know whether I can assign different currency for each resources... ? For Ex: Resource1 : INR Resource2: USD Plz help me.. Thanx
  • 2. domain and non-domain on the same server
    is it possible to authenticate domain and non-domain users to the same project 2003 server ? .. i've been playing around and only seem to be able to get one or the other, checking the extranext settings from the manual and setting the virtual directory site to anonymous works for non domain, but then stops domain users getting in.
  • 3. PWA Filtering on Current Date
    Hi, I am trying to create a custom View in PWA that shows all of the tasks that finish anytime between the current date and a week from now. I can set the first part of the filter: "Finish - Greater Than or Equal To - Today" But how can I set the second constraint? I basically want it to say: "Finish - Less Than or Equal To - Today + 7" but Project wont accept the syntax "Today + 7". How do I get it to dynamically calculate the second constraint date? This filter needs to be included in the view as I don't was users themselves setting it up. Can anybody help? Thanks in advance, MDWigs

predecessors and successors

Postby Ingrid » Wed, 30 Jul 2003 15:57:53 GMT

I am using 4 project files linked to each other in a master
file.  The predecessors and successors don't seem to have
any pattern for when they appear and when they don't.  Eg.
a task in one project(project A) may have three successors
in another one (project B), yet only two show up in project
A in the task list of a gantt chart.  


I've tried turning the "show external sucessors" on and off
in Tools>Options but this doesn't actually hide them all or
show them all - I still get some showing and some not
showing.  

Any ideas how to get some consistency with these?

Thanks, 
Ingrid


Re: predecessors and successors

Postby Jack D. » Thu, 31 Jul 2003 04:39:08 GMT



I think that if all the subprojects are expanded then you will see the
linkages.
But other than that, I find that they are somewhat capricious.

-- 
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check  http://www.**--****.com/ 

-Jack Dahlgren, Project MVP


+++++++++++++++++++



Similar Threads:

1.Two links from predecessor to successor

Please help urgently,im using microsoft project on construction project,i 
need to link two task by using two links SS and FF ,I have tried but i get 
error

Regards,


Lulanga

2.External Predecessors and Successors

I have many External Predecessors and Successors within my schedules.
When looking at Tools, Options, View - Cross project linking options for 
'project name' some of the link show and some do not! It seems not to be 
consistent which ones it omits and which ones it doesn't.

Has anyone seen (or not seen) this before?

Does anyone have a remedy?

Cheers,

Russ.

3.Display Predecessor and Successor Task Names

I want to display for each task row any predecessor and successor task names 
that the task has.
I want to do this because the procject is relatively large.
I think I should use a customized text field. However, I am unsure how to 
code the formula to pull the task name.
Any advice would be appreciated.
Thanks

4.synching predecessor and successor dates based on F-S link

Hi folks,

I'm working with MSP2003 and PS2003.  I have a project with afew tasks that have predecessor - successor relationships.  They are F-S.  Some have a lag, some have a lead time, some have neither.  The issue I have is that when the finish date changes for a predecessor task, the start date for the successor remains unchanged.  I've checked the calculation settings and it is set to recalculate automatically.

For example

Task 115 is a predecessor for task 117.  T115's end date is June 28.  T117's start date is June 30.  If I change T115's end date to July 7, the startdate for T117 remains set to June 30.

Thanks for any insights.

Jim

5.Project: Self Modify the Predecessor and Successor Windows

6. Project: Jump to a predecessor or successor by double clicking it

7. Importing from Ecxel, using WBS predecessor/WBS successor

8. Wrapping Predecessor or Successor Field



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 11 guest