predecessors and successors

Microsoft Project

    Sponsored Links

    Next

  • 1. PERT Analysis
    MS Project help refers to a PERT analysis COM Add-in to perform PERT analysis. I have not been able to locate it on Microsoft's site or with the software. Does anyone know how to get this add-on?
  • 2. Project 2002 Critical Path problem
    Hey i cant seem to figure this out, im having problem with a task overlapping one that is linked. I have a delivery date set, and a installation date below it is linked to. But i want the date to be able to fluxuate, just in case of a delay. so if i move the delivery date and it overlaps the install date, it will go critical, but it just moves the install date over without telling me its done anything, i tried to set to must start on, but u cant fluxuate it which i want to. ive tried everything, the install date keeps moving and i dont want that. Thanks
  • 3. About Transfer Calendar Entries
    What does feature Transfer Calendar Entries mean? Please enlight me ... What is the objective of that feature?
  • 4. Vulnerable Security when Log on using a different Microsoft Windows user account
    Hi All, I think this is a critical problem because related to security issue. The problem is: I log on my friend PC, so I use feature "Log on using a different Microsoft Windows user account". After I finished using Project Central/Server then I log off. BUT, when my friend klik button "Log on using a different Microsoft Windows user account", my friend can access Project Central with my account directly. There's no form come out to ask username and password. It directly go through Project Central with my account. Anybody can help me to solve this. Is ther something I have to re-configure?
  • 5. Deleting a Project from MS Server
    Okay, I feel pretty stupid on this one. But how do you delete an unwanted Project from MS Project Server? Its driving me nutty! Any help would be greatly appreciated! Thanks, Brad

predecessors and successors

Postby Ingrid » Wed, 30 Jul 2003 15:57:53 GMT

I am using 4 project files linked to each other in a master
file.  The predecessors and successors don't seem to have
any pattern for when they appear and when they don't.  Eg.
a task in one project(project A) may have three successors
in another one (project B), yet only two show up in project
A in the task list of a gantt chart.  


I've tried turning the "show external sucessors" on and off
in Tools>Options but this doesn't actually hide them all or
show them all - I still get some showing and some not
showing.  

Any ideas how to get some consistency with these?

Thanks, 
Ingrid


Re: predecessors and successors

Postby Jack D. » Thu, 31 Jul 2003 04:39:08 GMT



I think that if all the subprojects are expanded then you will see the
linkages.
But other than that, I find that they are somewhat capricious.

-- 
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check  http://www.**--****.com/ 

-Jack Dahlgren, Project MVP


+++++++++++++++++++



Similar Threads:

1.Two links from predecessor to successor

Please help urgently,im using microsoft project on construction project,i 
need to link two task by using two links SS and FF ,I have tried but i get 
error

Regards,


Lulanga

2.External Predecessors and Successors

I have many External Predecessors and Successors within my schedules.
When looking at Tools, Options, View - Cross project linking options for 
'project name' some of the link show and some do not! It seems not to be 
consistent which ones it omits and which ones it doesn't.

Has anyone seen (or not seen) this before?

Does anyone have a remedy?

Cheers,

Russ.

3.Display Predecessor and Successor Task Names

I want to display for each task row any predecessor and successor task names 
that the task has.
I want to do this because the procject is relatively large.
I think I should use a customized text field. However, I am unsure how to 
code the formula to pull the task name.
Any advice would be appreciated.
Thanks

4.synching predecessor and successor dates based on F-S link

Hi folks,

I'm working with MSP2003 and PS2003.  I have a project with afew tasks that have predecessor - successor relationships.  They are F-S.  Some have a lag, some have a lead time, some have neither.  The issue I have is that when the finish date changes for a predecessor task, the start date for the successor remains unchanged.  I've checked the calculation settings and it is set to recalculate automatically.

For example

Task 115 is a predecessor for task 117.  T115's end date is June 28.  T117's start date is June 30.  If I change T115's end date to July 7, the startdate for T117 remains set to June 30.

Thanks for any insights.

Jim

5.Project: Self Modify the Predecessor and Successor Windows

6. Project: Jump to a predecessor or successor by double clicking it

7. Importing from Ecxel, using WBS predecessor/WBS successor

8. How to Audit Predecessor and Successor Relationships in Project Pl



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 23 guest