predecessors and successors

Microsoft Project

    Sponsored Links

    Next

  • 1. Registering MS Project.
    Hi All I am new to MS project. I have installed MS project 2002 and registered the details while opening for the first time as it asked to register the details. Now I would like to unregister this.How can I do this...? I have uninstalled the product , is that enough to unregister it ... Thanks and regards -Santhosh
  • 2. How do i find a german proofing download for office 2000?
  • 3. Automatic Formatting of Gantt Bars
    I'm working with Project 2002 standard. I have a master plan with multiple projects inserted to represent the program I am managing. I would like MS Project to automatically change the color of the summary bars to match a Status field (Example - Green indicating on schedule, Red behind). I'm sure this is possible, but how difficult is it?
  • 4. Global.mpt fails to load on startup
    When I open Ms Project 2002 on my laptop, I get the message failed to load global.mpt. Project then opens with the global file. When I exit out of Project I am prompted to save Global.mpt. This problem will not allow me to open any saved files in Project. I have been having this problem from the start. I have installed the service pack for the product, reinstalled project, deleted the Global.mpt file but still get the same message. I also had the same problem with Word 2002 a few months ago. Any Ideas?
  • 5. "Compressed" resource graphs
    Hi Is there any way in Project (2000 or above) to display a "compressed" version of the resource graphs so you can see several on one page rather than having to scroll though every resource graph? Would it be possible to show only over-allocated resources so attention can be focused on leveling those? Thanks Clive

predecessors and successors

Postby Ingrid » Wed, 30 Jul 2003 15:57:53 GMT

I am using 4 project files linked to each other in a master
file.  The predecessors and successors don't seem to have
any pattern for when they appear and when they don't.  Eg.
a task in one project(project A) may have three successors
in another one (project B), yet only two show up in project
A in the task list of a gantt chart.  


I've tried turning the "show external sucessors" on and off
in Tools>Options but this doesn't actually hide them all or
show them all - I still get some showing and some not
showing.  

Any ideas how to get some consistency with these?

Thanks, 
Ingrid


Re: predecessors and successors

Postby Jack D. » Thu, 31 Jul 2003 04:39:08 GMT



I think that if all the subprojects are expanded then you will see the
linkages.
But other than that, I find that they are somewhat capricious.

-- 
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check  http://www.**--****.com/ 

-Jack Dahlgren, Project MVP


+++++++++++++++++++



Similar Threads:

1.Two links from predecessor to successor

Please help urgently,im using microsoft project on construction project,i 
need to link two task by using two links SS and FF ,I have tried but i get 
error

Regards,


Lulanga

2.External Predecessors and Successors

I have many External Predecessors and Successors within my schedules.
When looking at Tools, Options, View - Cross project linking options for 
'project name' some of the link show and some do not! It seems not to be 
consistent which ones it omits and which ones it doesn't.

Has anyone seen (or not seen) this before?

Does anyone have a remedy?

Cheers,

Russ.

3.Display Predecessor and Successor Task Names

I want to display for each task row any predecessor and successor task names 
that the task has.
I want to do this because the procject is relatively large.
I think I should use a customized text field. However, I am unsure how to 
code the formula to pull the task name.
Any advice would be appreciated.
Thanks

4.synching predecessor and successor dates based on F-S link

Hi folks,

I'm working with MSP2003 and PS2003.  I have a project with afew tasks that have predecessor - successor relationships.  They are F-S.  Some have a lag, some have a lead time, some have neither.  The issue I have is that when the finish date changes for a predecessor task, the start date for the successor remains unchanged.  I've checked the calculation settings and it is set to recalculate automatically.

For example

Task 115 is a predecessor for task 117.  T115's end date is June 28.  T117's start date is June 30.  If I change T115's end date to July 7, the startdate for T117 remains set to June 30.

Thanks for any insights.

Jim

5.Project: Self Modify the Predecessor and Successor Windows

6. Project: Jump to a predecessor or successor by double clicking it

7. Importing from Ecxel, using WBS predecessor/WBS successor

8. Wrapping Predecessor or Successor Field



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 33 guest