predecessors and successors

Microsoft Project

    Sponsored Links

    Next

  • 1. HP Desktop for sale!
    Hi, I have an unused HP Pavilion with the fallowing specs: # Processor: AMD Athlon 64 X2 4000+ (2.1GHz, 2000MT/s System Bus) # Memory: 2048MB PC2-5300 DDR2 SDRAM memory (2x1GB) (expandable to 8 GB (4 x 2 GB) (64-bit OS)/ 4 GB (4 x 1 GB) (32-bit OS)) # Hard Drive:320GB 7200RPM SATA 3G (3.0 Gb/sec) hard drive # Optical Drive: 16X DVD(+/-)R/RW 12X RAM (+/-)R DL LightScribe SATA drive # Expandable Drive Bay: HP Pocket Media Drive bay # Video Graphics: Integrated graphics # Network Interface: Integrated 10/100BaseT network interface # Sound: High Definition 8-channel audio # Fax/Modem: 56K bps data/fax modem # Operating System: Genuine Windows VistaHome Premium This is "used" but basically brand new (it has literally been on for no more than 6 total hours..) is only 1 month old.. PRICE: $425 OBO Email- XXXX@XXXXX.COM
  • 2. Use project to represent over-all progress and detail progress (how to)
    Hello MS Project - I would like to set up a sked for project. The project is writing 10 scripts for 10 tutorials (kinda like flash movie, elearning, etc) There is basically 1 script per tutorial. I would like to have a sked for the "Tutorials" project - which would be a roll-up of each script. This would be a schedule to track each tutorial from "write the script" to release the tutorial. Each script would have the same tasks: write, edit, show others, review, incorp any changes, the record the script, and release the tutorial. I would like to have each script on my master sked, with details showing for each script. Kind of like a the task/subtask display in project. Does this make sense for the application? I would basically have 10 scripts, with the same tasks (more or less), that would roll up to a higher level.

predecessors and successors

Postby Ingrid » Wed, 30 Jul 2003 15:57:53 GMT

I am using 4 project files linked to each other in a master
file.  The predecessors and successors don't seem to have
any pattern for when they appear and when they don't.  Eg.
a task in one project(project A) may have three successors
in another one (project B), yet only two show up in project
A in the task list of a gantt chart.  


I've tried turning the "show external sucessors" on and off
in Tools>Options but this doesn't actually hide them all or
show them all - I still get some showing and some not
showing.  

Any ideas how to get some consistency with these?

Thanks, 
Ingrid


Re: predecessors and successors

Postby Jack D. » Thu, 31 Jul 2003 04:39:08 GMT



I think that if all the subprojects are expanded then you will see the
linkages.
But other than that, I find that they are somewhat capricious.

-- 
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check  http://www.**--****.com/ 

-Jack Dahlgren, Project MVP


+++++++++++++++++++



Similar Threads:

1.Two links from predecessor to successor

Please help urgently,im using microsoft project on construction project,i 
need to link two task by using two links SS and FF ,I have tried but i get 
error

Regards,


Lulanga

2.External Predecessors and Successors

I have many External Predecessors and Successors within my schedules.
When looking at Tools, Options, View - Cross project linking options for 
'project name' some of the link show and some do not! It seems not to be 
consistent which ones it omits and which ones it doesn't.

Has anyone seen (or not seen) this before?

Does anyone have a remedy?

Cheers,

Russ.

3.Display Predecessor and Successor Task Names

I want to display for each task row any predecessor and successor task names 
that the task has.
I want to do this because the procject is relatively large.
I think I should use a customized text field. However, I am unsure how to 
code the formula to pull the task name.
Any advice would be appreciated.
Thanks

4.synching predecessor and successor dates based on F-S link

Hi folks,

I'm working with MSP2003 and PS2003.  I have a project with afew tasks that have predecessor - successor relationships.  They are F-S.  Some have a lag, some have a lead time, some have neither.  The issue I have is that when the finish date changes for a predecessor task, the start date for the successor remains unchanged.  I've checked the calculation settings and it is set to recalculate automatically.

For example

Task 115 is a predecessor for task 117.  T115's end date is June 28.  T117's start date is June 30.  If I change T115's end date to July 7, the startdate for T117 remains set to June 30.

Thanks for any insights.

Jim

5.Project: Self Modify the Predecessor and Successor Windows

6. Project: Jump to a predecessor or successor by double clicking it

7. Importing from Ecxel, using WBS predecessor/WBS successor

8. Wrapping Predecessor or Successor Field



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 87 guest