Similar Threads:
1.Stop Actual Work from impacting Work
Hi, is it possible to enter a value in the actual work field without it
making a change to the work field?
In the timephased portion of the task usage view I enter a vlaue in the
actual work cell for a given day but I don't want the work cell to change. So
for a task that has work of 8 hours, I entered actual work of 5. I would like
for work to remain at 8.
Looking forward to answer. Thanks!
2.Entering values in Budget Cost & Budget Work in msp2007
I have the columns set up in my Resource Sheet, next to cost and work, but am
not able to enter values in either Budget Cost or Budget Work columns, and I
don't understand why. Also, is there a way of linking those cells, or at
least simply copying the data from Work to the Budget Work, and likewise for
copying cost to Budget Cost?
--
John from NY
3.Disable fileds in 'My work' (MSP2007)
hi,
In ' My Work' view Start & Finish fields are mandatory fields
I want to disable the start date.
Can i disable the fields ?
--
shoham B
4.Holidays / non-working days for MSP2007
Hello,
Are there any tables that stored the information regarding the
holidays or non-working days at all in MSP2007? I think in 2003, I saw
something like MSP_CALENDARS and MSP_CALENDAR_DATA.
When the admin entered the Company's holidays into the MSP2007, what
tables that the holidays or non-working days information go? I realize
that the resource timesheets can be grayed out because the days have
been designated as a non-working days or holidays.
For example, Friday after Thanksgiving might be the holiday on some,
but it was the working days for many employers.
Some of the posts recommended using dbo_MSP_EpmResourceByDay_UserView
to differentiate the working and non-working days. Is this the only
way?
I do appreciate your time responding to the questions. Thank you.
5.Simple Work View for a Resource
Hello,
Is there a way to simply see a normal monthly calendar view (like the
'month' calendar you see in Outlook) where it clearly denotes which days of
the month a resource is scheduled to work?
I have a 3 month long project and I want to send each resource a view
indicating "Here are your scheduled days of work. Plan your vacation
accordingly."
Many Thanks!
6. VBA routine for Project to Edit Taskname field
7. Publishing routine when using MASTER projects.
8. Looking for VBA routine