Rnd Function in Custom Field

Microsoft Project

    Sponsored Links

    Next

  • 1. Pricing MS Project
    i was charged to find out how much will cost to deploy microsoft project to more than 100 users.somebody mentioned we should get a "site" license for ms project. any help where i should start? i checked microsoft's website but i couldn't find exact pricing info by the number of users. thanks
  • 2. MS Project 98
    I need some help setting up my HP DesignJet 430 to accept Microsoft Project 98 "Schedule Plot" I get a good preview and when it plots the fires 95% of the schedule comes oput blank and the description comes out with only half showing diagonally from the top to the lower left hand corner blank. What do i need to do? Angelo Scozzarella XXXX@XXXXX.COM
  • 3. group by ??
    In MS Project 2000 there is a function called "group by". I have a MSP2000-file that contains "group by" and now I wonder if anyone knows if it's possible to somehow use this in a MS Project 98 version since this function is not installed in that version ?
  • 4. Connect Database - part2
    Hi! Through the 'projdb.htm' file I could see that we can use SQL instructions to write data into a specific table. What I would like to know is if there's a way of doing so without having to write the data in the instruction. The people that are going to use the database I'm building aren't confortable with SQL or VBA, so I'd like to come up with an easy sollution for their problem (exporting and importing data to and from Project, to and from Access. Can anyone help me please? Thanks in advance! Manuela
  • 5. Professional Scheduling
    My organization uses something called professional scheduling. It works something like this: - An employee is salaried, let's say $1000 per week. This calculates out to $25/hour - Technically, he will work 40+ hours per week - He's assigned several tasks to complete during the week. For simplicity sake, let's say 5 and each takes 8 hours each. If he works 40 hours during the week, the cost associated to completing these tasks will be $25 per hour. If he works less than 40 it's still $25 per hour because the other time is taken up with something else (i.e. sick pay, vacation, etc). Easy! Now, if he works 48 hours, 12 hours each on two of the tasks and 8 hours on the other three, everything changes. He still only gets $1000 for that weeks work, but now it calculates out to $20.83 per hour. In other words, the hourly rate used to calculate the cost of the assignment depends on how many hours he actually works, if he works over 40 hours. Is there an easy way to set this up, or do I have to write a VBA script that will recalculate a persons rate every week, based on the actual hours he/she worked, then enter it, with a date, as a new entry into the cost rate table? If this is how it needs to happen, do you have any suggestions? I'm not new to VBA programming, but I am in Project programming. Thx

Rnd Function in Custom Field

Postby U2NvdHQgRA » Wed, 12 Jul 2006 02:06:02 GMT

I am trying to create a custom field that will round up or just simply round 
off the duration of the tasks.  Ie found the syntax for the round function, 
Rnd(number), I've tried the following syntax scenarios Rnd(Duration) which 
yields "0 days".  What I want to use is Duration Variance but it will not 
allow the following syntax, Rnd(Duration Variance) I get a message that tells 
me the syntax is wrong.  Ie tried Rnd("Duration Variance") and it yields 
#ERROR.  Ie tried Rnd([Duration Variance]) and it yields  days  What do 
I need to do to the field name to make it work?
-- 
And they said this would be easy

Re: Rnd Function in Custom Field

Postby Jan De Messemaeker » Wed, 12 Jul 2006 02:35:56 GMT

Hi,

Rnd is the function that generates a random number beween 0 and 1.
Better use Fix or Int.



Re: Rnd Function in Custom Field

Postby Um9nZXI » Wed, 12 Jul 2006 05:15:02 GMT

Try: Round([Duration Variance]/[Minutes Per Day])






Re: Rnd Function in Custom Field

Postby Jan De Messemaeker » Wed, 12 Jul 2006 05:42:12 GMT

Hi,

I can't find Round in the MS project custom field function list, nor in the
help.
The urprising thing is: it works.



Re: Rnd Function in Custom Field

Postby John » Wed, 12 Jul 2006 06:10:27 GMT

In article < XXXX@XXXXX.COM >,




Scott,
A couple of added comments. If you are using a spare duration field for 
your custom field, the Fix or Int functions will not work. I'm not sure 
why but they just don't - it may have something to do with the 
formatting applied to spare duration fields. A spare text field will 
work fine although you will need to apply a factor if for example you 
want the value in days, (Project stores all time related information in 
minutes, so to convert to days a factor of 490 must be used).

If you really want a rounded value instead of a truncated value, use the 
rounding function. It is not listed as being available for custom field 
formulas, but it will work. The syntax is:
Text1 = Round([Duration Variance]/480)

Hope this helps,
John
Project MVP


RE: Rnd Function in Custom Field

Postby U2NvdHQgRA » Thu, 13 Jul 2006 06:17:02 GMT

First ya'll are quick to respond, I appreciate the help.

But, its still not working (for me).  

Fix and Int aren't producing any change at all, my days are still going out 
to a decimal place.

Round([Duration Variance]/[Minutes Per Day]) divides my days by 480 and 
reduces them to fractions of days unless the task exceeds 480 days.

Text1 = Round([Duration Variance]/480) yields "0 days" in all tasks.

I've tried  Round([Duration Variance]) and I get not change, I've tried 
placing a comma and a zero or a whole number after [Duration Variance], like 
you would in a spreadsheet and nothing changes.  Could there be something in 
the customization of the project that needs to be checked?  If you haven't 
notice by now, I'm still new at using this program.







-- 
And they said this would be easy





> #ERROR.  Ie tried Rnd([Duration Variance]) and it yields  days  What do >
> I need to do to the field name to make it work?>
> -- >
> And they said this would be easy

Re: Rnd Function in Custom Field

Postby Jan De Messemaeker » Thu, 13 Jul 2006 15:56:37 GMT

Hi,

We all should have been more explicit.
The reason some of the "solutions" offered work and others don't is that
Project KEEPS durations in minutes, but inDuration columns SHOWS them as
whatever you like (default days). So when you use any formula, the values in
there are inevitably in minutes.
So let's say you have a duration variance of 2,25 days or 600 minutes.
When your formula is Round([Duration Variance]) it is calculated to 600
(which is round so cannot be rounded) and displayed again a 2,25
The only solution thus consists of dividing duration variance by 480 (or to
be more precise, should you have a day definition other than 8 hours, by
Minutes Per Day, a value to be found under Field, Project, Number) and round
the result.
That works perfectly when you put iy IN A NUMBER FIELD because a number
foeld will not try to display it in any other unit than what is calculated.
The value shown will be 2.
However, in a duration field, Project will convert this value of 2
(remember, if it's duration, it is interpreted as minutes) into days and
show you 0 because rounded at 2 decimals it's les than 0,01.
So if you want the result in a duration field you have to do the conversion
the other way around again and the formula will be:

[Minutes Per Day]*Round([Duration Variance]/[Minutes Per Day])

That's it..

Greetings,



Re: Rnd Function in Custom Field

Postby U2NvdHQgRA » Thu, 13 Jul 2006 23:53:01 GMT

an

Thanks for simplifying it for me. It worked exactly like I wanted it to.
I've got to quit treating the functions as if I were in a spreadsheet.

Scott
--
And they said this would be easy


"Jan De Messemaeker" wrote:


Re: Rnd Function in Custom Field

Postby Jan De Messemaeker » Fri, 14 Jul 2006 00:42:02 GMT

Hi Scott,

You're welcome.
And I doin't know whether easy is the word, but by all means

- it is NOT a spreadsheet indeed
- and it is rarely "intuitive"

Greetz,



Similar Threads:

1.Adding a function into Custom Field, Formula

2.Switch Function for Custom Field Formulas

I am attenpting to use 

switch(expr1, value1, expr2, value2, expr3, value3)

After entering 14 expr/value pairs I receive a syntax 
error.  Does anyone know if there is an upper limit on 
the number of expr/value pairs that can be entered into a 
switch statement?

Thanks.

Marian

3.#ERROR message for custom field function - Bizarre!

I hope someone can help me understand this bizarre problem with a project 
plan that I've been using and evolving for the past 1 1/2 years to track a 
number of projects on a very high level (Project Portfolio Reporting):

All of a sudden my custom field functions no longer work - even a simple 
Today = Now() function.  It results in "#ERROR" being displayed.  I checked 
to make sure that I did not remove any necessary custom fields, tables, etc. 
that are used by other calculations. (All looks good)  I confirmed that I 
have the auto-calculate value set under Tools -> Opotions-> Calculation mode. 
 I pushed the F9 key just in case as well. If I create a band new project and 
I test the "Now()" function in a custom field it works great.  

THEN I stumbled onto a fix by adding a bogus new task to my existing file 
and all of a sudden everything recalculated and the function returned the 
proper value???  Can anyone tell me what is going on??  It is as if MS 
Project decided to do a 'recalculate' with this new task I added and then all 
is good.  

Please help me understand what is going on!
Thank you SO much!

4.project functions for custom fields

I'm trying to use project functions for custom fields. in particular the 
'format' function. I'm having a hard time finding documentation on what the 
various options/commands available are and how to use.

help?

5.Custom Ent Fields - Functions

I've defined a project status field with an associated pick list. In my view however, I want to replace the single numeric value with the descriptive field. What function is best for doing this?

Examples: 1=Pre-approval; 2=Approved; 3=Complet

6. Using Task IDs in Custom Field Functions

7. Custom functions for customised field formulae

8. Aggregate functions (min, sum) in Custom Project Fields



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 38 guest