Sub-sub tasks under sub-tasks

Microsoft Project

    Next

  • 1. Resource Usage Report Summarised by Outline Level and Resource Group
    Project 2003 ========== I want to be able to have a report, I think the Resource Usage is the place to do this, that shows me at the activity level, just Outline Level 1 summaries, and then within that I want to know the work by Resource Group. So for example I want to see :- Phase 0 Customer 25 days Supplier 30 days Phase 1 Customer 13 days Supplier 12 days But I'm struggling, if I do the Customize Group By and group by Task Outline Number, then Group I get all of the outline levels, not just Outline Level 1, and I can't seem able to use the "Define Groups Intervals...." to get what I want. Suggestions? Thanks David
  • 2. Change Request form
    Is there any sort of change request form in project server 2003. I haven't seen anything resembling one but my boss heard that there might be.
  • 3. Openeing & Saving MSP2000 files with MSP2003
    Guys, I just installed MSP2003 and I now have the following problems. I have posted before for a similar problem but this time the symptoms are different. Her's what's happening: I open an existing MSP2000 file with MSP2003. I edit the file. Then, when I want to save it I have the following message: "The file cannot be opened" * Check that the file name and path are correct. * Check that the file format is recognized by Project. Project files saved in a version earlier than Microsoft Project 98 can't be opened. If your file is from an earlier version, open it in that version, click ..." I then close the file without saving, try to re-open and can't! The file seems to be corrupted to the point that it can't be opened anymore & MSP2003 is generating a failure report that I do send. Helppppppppppppppppppp !!!!!!!!!!! Big_Bad
  • 4. Templates/columns
    How do I restore the ID column after it was hidden from view and the data that was associated with the column. I am using Mircosoft Project 2003 Standard.

Sub-sub tasks under sub-tasks

Postby binojkr » Wed, 23 Jul 2008 16:20:22 GMT

I am a novice to MS Project.



I have a project management requirement as follows:


I want to monitor and manage some seven sub-sub tasks under some 20 su
tasks. To make it more clear, I want to monitor the Drawing sheet statu
of plan, elevation, section etc(7 of them in general, but if there ar
multiple sheets for sections, then the number goes up). These are m
sub-sub tasks. These appear under some 20 odd areas like single room
double room, lobby etc.. which I assume are sub tasks. 

In excel i could use multiple sheets and a row colum matrix of 20x7 t
manage this problem. In MS Project, I did not come across any suc
facility of row column matrix or linking multiple sheets kind of stuff
Since MS Project deals with each sub (sub-sub) task as a row, I presum
that I must have 20x7 = 140 odd rows, with the same kind of names (pla
elevation...) repeated, making it combursome and difficult t
understand. 
Moreover, I may have to include yet another sub level under a few o
these sub-sub levels.

How do I solve this problem? 

Pls help.



Thanks a lot in advance.

Binoj.  XXXX@XXXXX.COM 

 http://www.**--****.com/ 


RE: Sub-sub tasks under sub-tasks

Postby QiBTYWkgUHJhc2FkIFtQTVBd » Wed, 23 Jul 2008 18:36:04 GMT

Dear Binojkr -

I understand you have the executable tasks in each sheet of workbook. 

The fundamental idea is to consider each sheet "name" of the workbook as 
summary task / phase in the schedule and have the rows in each workbook as 
individual (executable) tasks in the schedule.

As you a beginner to Microsoft Project, I would like to suggest the 
following approach to migrate the data from workbook to Microsoft Project.

1. Open MS Project and choose File, Open to use the Import Wizard to map the 
columns in sheet to fields in MS Project. 
2. Repeat step 1 for each sheet in the workbook
3. Now, it would be cumbersome for you to understand the schedule due to the 
size and all the tasks are in the same level. So, you can insert rows between 
the different phases - like plan, elevation, section 
4. Select (only) the "executable" tasks under the phase and choose Indent 
(->) arrow in Formatting tool. This will push these tasks and outline the 
schedule.

If my suggestion is useful, consider rating it :-)

-- 
Regards
Sai
* Enjoy scheduling with Microsoft Office Project *






Re: Sub-sub tasks under sub-tasks

Postby Steve House [MVP] » Thu, 24 Jul 2008 01:58:17 GMT

Project is certainly able to handle that level of complexity, piece of cake. 
The outline structure can theoretically accomodate up to 65000 levels of 
indentation.  But you are correct that you will have many of your 
performance tasks repeated.  The task list is essentially decomposed by 
deliverable so you'll end up with

Paint Interior
    Paint Living Room
        Prep Walls
        Paint Walls
            Mix Paint
            Apply Paint
        Cleanup drips
    Paint Master Bedroom
        Prep Walls
        Paint Walls
            Mix Paint
            Apply Paint
        Cleanup drips
etc
etc
etc







Similar Threads:

1.Summary task does not pick up finish date of sub-tasks

I have a summary task that has multiple sub-tasks.  I changed all of the 
sub-task finish dates (and removed all constraints of the sub-tasks) and the 
summary task continues to reflect the original finish date (two months later 
than new date).
There are no predecessors, no links, no constraints set.
Help please! Thank you.

2.After changing sub task dates, summary task doesn't update

I've change the dates on a few of the sub task and the Summary task doesn't 
refelect any of the date changes. I've tried this with other tasks in this 
project plan and the same issue occurs. The last time I was in this plan I 
was able to do this successfully. Any help would be appreciated.

3.Task Duration (days) Sub-task Duration (wks)

How do I change the task duration to weeks as I am showing the subtask in 
weeks.
I am being restricted to days on the original task as I indent the subtasks.

4.Hiding Main tasks instead of sub-tasks

I have a massive project with way too many task and sub-tasks.  I know one 
can hide sub-tasks but clicking the "-" sign next to the main task. However I 
need a way to hide the main task since in some cases it creates clutter. 

The start and end date for the main task is the start and end date of all 
the sub-tasks,so the main task doesn't have any pre/successor.

Thanks for the help

5.sub task occurring outside summary task dates!

Has anyone ever seen a schedule where the sub task bar on the Gantt
chart extends out and starts before it's summary tasks? I am told the
file was created in Excel, then transferred in. Can send a gif, it you
like. Or maybe I took one to many acid trips back in the sixties....

Dave Bellamy
Bellamy Consulting

6. Breaking a task down into it's sub tasks

7. assigning more than one parent task to a sub task

8. Showing Tasks and Sub-Tasks in the Calendar View



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 7 guest