I can't figure out how to get the roll up in custom fields to automatically update when new values are entered. I always have to hit the "calculate project" button Any way to get them to automatically update like the standard fields do JLR
I can't figure out how to get the roll up in custom fields to automatically update when new values are entered. I always have to hit the "calculate project" button Any way to get them to automatically update like the standard fields do JLR
JLR: Modify your custom field. Go Tools, Customize, Fields, select the custom field you want to remodify. About half way down the custom field dialog box there is a section entitled "Calculation for task and group summary rows." You should select Rollup - Sum. If after this, the field still doesn't calculate automatically, check your calculation options and make sure calcs are set to automatic. Good Luck! --------------------------- Sean Pales EPM Solutions Group Bennett Adelson www.bennettadelson.com fields to automatically update when new values are entered. I always have to hit the "calculate project" button. standard fields do?
1.Customised field roll-ups seem to be screwy
This is a repeatable bug across my project. I have a project which I am working backwards from a deadline, so the tasks are all set to "As late as possible". The tasks are put at one point in time, but the task roll ups dates seem to default to now. Example: - Task Summary 40 days 1/4/2005 10/5/2005 Task item1 20 days 1/8/2010 20/8/2010 Task item2 20 days 21/8/2010 10/9/2010 (note the summary dates do not match the task item dates) Any ideas if there is a fix for this problem? Thanks R
I need some help understanding how resources work and baseline work roll up in the resource usage view. Here is the process: (we are using Project 2000) We saved 3 tasks all done by the same resource that were under a summary bar and the summary bar to a baseline. Total hours and baseline hours were 240 hours when you viewed the resource usage view. Next we added another task for the resource under the summary bar and saved just that task as a baseline. Now if you view the resoruce usage view for the resource. The baseline work for that resource is 240 hours, but the work is 320 hours. If you look at the task usage view you see the same difference. This is what I have seen before. However I would expect the resource usage view to not have this behavior. Is this correct? How does project calculate the resource summary information? thanks.
4.Baseline Value Roll-ups no working
I'm grouping my resources by the various work areas in-house. When I use the resource usage view, to do the breakout, it won't sum up the Baseline Work or Baseline Cost values. If I use cost and work alone , it sums up fine. What's the deal?
Users browsing this forum: No registered users and 77 guest