Duration Question Mark

Microsoft Project

    Sponsored Links


  • 1. printing all filtered tasks
    i have 200 tasks. after applying a filter, only 100 remain. Not all of these fit on the screen. I'd like to use a Copy Picture command within a macro. However, before doing so i need for it to select all tasks, including those that don't fit on the screen (but NOT those that were filtered, of course). Is there code for this? thanks scott
  • 2. Display from beginning of week?
    Is there some sort of setting where i can tell it to start out from the beginning of this week? For example, each time i run a macro telling it to display 1 week, I want it to start that one week at the beginning of the current week. Right now it is starting wherever the scrollbar happens to be. thanks scott
  • 3. Custom Form
    I want to customize the Task Information form, but when I go to Tools > Customize > Forms, that form is not listed as available for customization. The problem is that I have some dropdown lists that need to be in my form, and the custom form editor only gives me text boxes to work with. In addition, when someone double-clicks on a task, they get the Task Information form, which has items in it that I'm not using and don't want people editing. If anyone knows a way to get around these issues, through VB code for example, that would be great.
  • 4. Unique ID Successors
    Hi, Looking for some help, with project 2003. This seems quite complex so will describe the best I can I have a series of projects that are inserted into a programme plan, there are dependencies between projects which are dynamically linked within msp. In order to produce status reports for management I export data into excel, however I have found a problem with respect to predecessors and successors, and here goes : Example Individual Project Plan level (all seems to be fine here) Dependency within Project Plan has Unique id of 76 Has a successor of task 119 Successor task Unique ID 44 Therefore in column successor Unique ID 44 is shown Task at line 119 has a unique ID of 44 All is fine However when the above project is inserted into the programme level plan, the following occurs Dependency within Project Plan has Unique id of 348127308 Has a successor of task 119 Successor task Unique ID 44 Therefore in column successor Unique ID 44 is shown However the Unique ID of the successor (line 119 of the original project plan) is now 348127276 So to summarise the unique ID of the successor in the programme level plan is actually the unique id of the successor in the project level plan and thus I cannot trace the relationship between the two (I cant use the line id as all the inserted project will have a line id of 119) Any ideas ?

Duration Question Mark

Postby cassidym » Mon, 19 Nov 2007 23:44:43 GMT

What is the purpose of the question make in the Duration column and ho
do you make it disappear? 

I'm new to Project (an old hand at Access) so apologize for what i
probably a very rookie question. 

Sorry, I seem to have posted this question twice.  At least I admitte
to being a rookie.



Re: Duration Question Mark

Postby Mike Glen » Tue, 20 Nov 2007 02:46:27 GMT

Hi cassidym,

Welcome to this Microsoft Project newsgroup :)

The question mark indicates that the duration is tentative or estimated.
When you actually type in a figure for the duration, the question mark will
disappear.  Tools/Options.../Schedule tab has an option to switch this off.
However, it seems to me to be a very unnecessary facility as, after all,
aren't all the durations estimates?  If you leave the question marks there,
you can filter for uncertain durations to allow you to firm up the ones
you've missed.

FAQs, companion products and other useful Project information can be seen at
this web address:  http://www.**--****.com/ 

As a beginner, you might like to have a look at my series on Microsoft 
Project in the TechTrax ezine at this site:  http://www.**--****.com/ 
(Perhaps you'd care to rate the articles before leaving the site, :) 

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP

Re: Duration Question Mark

Postby John » Tue, 20 Nov 2007 02:49:24 GMT

In article < XXXX@XXXXX.COM >,

The question mark simply indicates that the duration is a best guess 
estimate. You can remove it under Tools/Options/Schedule. Uncheck the 
option to "show that tasks have estimated durations".

Project MVP

Re: Duration Question Mark

Postby Mike Glen » Tue, 20 Nov 2007 03:07:55 GMT

Incidentally, I forgot to mention that you can type in the duration with a 
question mark to bring it back again.

Mike Glen
Project MVP

Re: Duration Question Mark

Postby cassidym » Tue, 20 Nov 2007 07:07:05 GMT

One more question. Somehow, I've locked my initial task so that it onl
shows it's duration as equal to the combined durations of the subtasks

When I try to extend the finish date of the primary task, I can't ge
the calendar to open. The only way I can extend the time frame is t
add another subtask or extend the last one.

Obviously, I've changed a setting that is enforcing this

Any ideas what I did and how I can rectify it



Re: Duration Question Mark

Postby JulieS » Tue, 20 Nov 2007 10:54:07 GMT

Hello cassidym,

I assume you are talking about the project summary task (line zero). 
You have done nothing incorrect.  Summary task durations are calculated 
by Project and are the span of working time from the start of the 
earliest subtask to the finish of the last subtask.  As you note, the 
only way to change the duration is to change the schedule of the 

I hope this helps.  Let us know how you get along.

Project MVP

Visit  http://www.**--****.com/ 
about Microsoft Project

Similar Threads:

1.Question mark in Task Duration

Can anyone help with this simple problem?

Why does the Duration box in the Task Form have a question mark after
the estimated duration?

Typically I enter new tasks in the Task Form. My default Task Type set
to Fixed Work. I assign a Resource and enter the Work in the fields
provided. If the resource is not fully available, I adjust the Units.
The Duration box then gives me an estimate of how long the task will
take to complete. Nice. For example a 1 day task assigned to a 20%
resourse will take 5d to complete. But Project displays "5d?"  I don't
understand why sometimes there is a ? after the duration estimate and
sometimes not. Any ideas? 


2.Red mark and blue mark in timesheet hrs


For some of the task hrs in timesheet, the hrs shows red and for some the 
hrs shows blue color.

I understood that for approved ones the hrs shows black color. But, what it 
indicates when the task hrs shows red and blue color.

Any thoughts on this would be greatly appreciated.

Thank you
Shiva Chaitanya. 

3.Sub Task showing Days and Question Mark

4.? mark in Duration

I know this is a stupid question, but why do the ? marks show up in a 
duration? How can I get them to default to not showing up? How do I remove 
exisiting ones. I have just taken over a file from a client tha tis filled 
with them and Im on a time contraint.
I knowits some simple function that I am overlooking

5.What is the purpose of the question mark (?) in the duration field?

What is the purpose of the question mark (?) in the 
duration field? I know it is used to indicate an 
estimate.  Is that the only purpose - just an indicator?  
Does it server any other purpose or control how MS Project 
works in any way?

6. What is the purpose of the question mark (?) in the duration field

7. Fixed Duration Question

8. duration question

Return to Microsoft Project


Who is online

Users browsing this forum: No registered users and 62 guest