Duration Question Mark
by cassidym » Mon, 19 Nov 2007 23:44:43 GMT
What is the purpose of the question make in the Duration column and ho
do you make it disappear?
I'm new to Project (an old hand at Access) so apologize for what i
probably a very rookie question.
Sorry, I seem to have posted this question twice. At least I admitte
to being a rookie.
Thank
http://www.**--****.com/
Re: Duration Question Mark
by Mike Glen » Tue, 20 Nov 2007 02:46:27 GMT
Hi cassidym,
Welcome to this Microsoft Project newsgroup :)
The question mark indicates that the duration is tentative or estimated.
When you actually type in a figure for the duration, the question mark will
disappear. Tools/Options.../Schedule tab has an option to switch this off.
However, it seems to me to be a very unnecessary facility as, after all,
aren't all the durations estimates? If you leave the question marks there,
you can filter for uncertain durations to allow you to firm up the ones
you've missed.
FAQs, companion products and other useful Project information can be seen at
this web address: http://www.**--****.com/
As a beginner, you might like to have a look at my series on Microsoft
Project in the TechTrax ezine at this site: http://www.**--****.com/
this:
http://www.**--****.com/
(Perhaps you'd care to rate the articles before leaving the site, :)
Thanks.)
Hope this helps - please let us know how you get on :)
Mike Glen
MS Project MVP
Re: Duration Question Mark
by John » Tue, 20 Nov 2007 02:49:24 GMT
In article < XXXX@XXXXX.COM >,
cassidym,
The question mark simply indicates that the duration is a best guess
estimate. You can remove it under Tools/Options/Schedule. Uncheck the
option to "show that tasks have estimated durations".
John
Project MVP
Re: Duration Question Mark
by Mike Glen » Tue, 20 Nov 2007 03:07:55 GMT
Incidentally, I forgot to mention that you can type in the duration with a
question mark to bring it back again.
Mike Glen
Project MVP
Re: Duration Question Mark
by cassidym » Tue, 20 Nov 2007 07:07:05 GMT
One more question. Somehow, I've locked my initial task so that it onl
shows it's duration as equal to the combined durations of the subtasks
When I try to extend the finish date of the primary task, I can't ge
the calendar to open. The only way I can extend the time frame is t
add another subtask or extend the last one.
Obviously, I've changed a setting that is enforcing this
Any ideas what I did and how I can rectify it
Thnak
http://www.**--****.com/
Re: Duration Question Mark
by JulieS » Tue, 20 Nov 2007 10:54:07 GMT
Hello cassidym,
I assume you are talking about the project summary task (line zero).
You have done nothing incorrect. Summary task durations are calculated
by Project and are the span of working time from the start of the
earliest subtask to the finish of the last subtask. As you note, the
only way to change the duration is to change the schedule of the
subtasks.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://www.**--****.com/
about Microsoft Project
Similar Threads:
1.Question mark in Task Duration
Can anyone help with this simple problem?
Why does the Duration box in the Task Form have a question mark after
the estimated duration?
Typically I enter new tasks in the Task Form. My default Task Type set
to Fixed Work. I assign a Resource and enter the Work in the fields
provided. If the resource is not fully available, I adjust the Units.
The Duration box then gives me an estimate of how long the task will
take to complete. Nice. For example a 1 day task assigned to a 20%
resourse will take 5d to complete. But Project displays "5d?" I don't
understand why sometimes there is a ? after the duration estimate and
sometimes not. Any ideas?
Tks,
Cole
2.Red mark and blue mark in timesheet hrs
Hi
For some of the task hrs in timesheet, the hrs shows red and for some the
hrs shows blue color.
I understood that for approved ones the hrs shows black color. But, what it
indicates when the task hrs shows red and blue color.
Any thoughts on this would be greatly appreciated.
Thank you
Shiva Chaitanya.
3.Sub Task showing Days and Question Mark
4.? mark in Duration
I know this is a stupid question, but why do the ? marks show up in a
duration? How can I get them to default to not showing up? How do I remove
exisiting ones. I have just taken over a file from a client tha tis filled
with them and Im on a time contraint.
I knowits some simple function that I am overlooking
5.What is the purpose of the question mark (?) in the duration field?
What is the purpose of the question mark (?) in the
duration field? I know it is used to indicate an
estimate. Is that the only purpose - just an indicator?
Does it server any other purpose or control how MS Project
works in any way?
6. What is the purpose of the question mark (?) in the duration field
7. Fixed Duration Question
8. duration question