Duration Question Mark

Microsoft Project

    Sponsored Links


  • 1. Grid Error Using Web Access
    When using Microsoft Project Web Access while off site, I get an error when clicking on issues. The grid that should appear says loading data, then it stops and I get an error on page in the lower right hand corner of my browser. The error shows: Line:2325 Char: 5 Error: 'MSPJGrid.TextConv' is null or not an object Code: 0 URL: https://domain.com/projectserver/library/WssMain.asp?list=iss&_oid=-1 If I use a web browser to connect to Project Web Access while on site or while connected via VPN, I do not get this error. Any Ideas? Thanks, Randall
  • 2. cannot view cnn videos using IE6 and WMseries9
    I have tried for weeks to view cnn videos but haven't been sucessful. I have IE6 and WMPseries9 both have latest updates and WindowsME, also updated. Cnn downloads FLV_AUTO_FILE into my tempoary files and I still can't seem to open this file to play it. I have checked file type ext. .FLV and it says WMP will open this file. Does anyone know what my problem can be?
  • 3. Transfer Project table into word table
    Hello, I have a task table that I want to transfer to Word. I call it MyPJTable. I start a Word application called a1. Then I open a word document called w1. I insert a table called MyWdTable in w1 with the same number of columns as MyPJTable. There it stops. I cannot select cells in the PJ table so I can insert them one by one int the word table. I would like to do something like for r=1 to MyPjTable.rows for c=1 to MyPjTable.columns MyWordTable.range.cells(r,c).insertafter MyPjTable.cells(r,c).text next c MyWdTable.rows.add next r I cannot find out the total number of rows in the MyPjTable. It consists of a number of selected tasks. Any help please? Kamil
  • 4. Custom bars
    Is there any way to customize the bars in the Calendar view to reflect difference in the tasks?
  • 5. i want to know the first start date in a number of duplicate t
    John, thanks for your reply, I've already tried this 'SS' constraint and it provides me with the last start date for the group of tasks, what I was interested in was the first start date. Cheers Martin.. "John" wrote: > In article < XXXX@XXXXX.COM >, > Martin Theobald <Martin XXXX@XXXXX.COM > wrote: > > > I have a set of tasks, repeated for a number of different countires. > > I can create a summary milestone showing me the last finish date of each > > repeated activity, but what I'm looking for a way to create a summary > > milestone that shows when the repeated activity first starts. > > Martin, > If you already have milestones marking the last finish then a similar > process should be used to indicate the first start. Simply set up a > milestone for each group and set the Predecessor of the milestone to be > "Start-to-Start" with the first task. > > Hope this helps. > John > Project MVP >

Duration Question Mark

Postby cassidym » Mon, 19 Nov 2007 23:44:43 GMT

What is the purpose of the question make in the Duration column and ho
do you make it disappear? 

I'm new to Project (an old hand at Access) so apologize for what i
probably a very rookie question. 

Sorry, I seem to have posted this question twice.  At least I admitte
to being a rookie.



Re: Duration Question Mark

Postby Mike Glen » Tue, 20 Nov 2007 02:46:27 GMT

Hi cassidym,

Welcome to this Microsoft Project newsgroup :)

The question mark indicates that the duration is tentative or estimated.
When you actually type in a figure for the duration, the question mark will
disappear.  Tools/Options.../Schedule tab has an option to switch this off.
However, it seems to me to be a very unnecessary facility as, after all,
aren't all the durations estimates?  If you leave the question marks there,
you can filter for uncertain durations to allow you to firm up the ones
you've missed.

FAQs, companion products and other useful Project information can be seen at
this web address:  http://www.**--****.com/ 

As a beginner, you might like to have a look at my series on Microsoft 
Project in the TechTrax ezine at this site:  http://www.**--****.com/ 
(Perhaps you'd care to rate the articles before leaving the site, :) 

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP

Re: Duration Question Mark

Postby John » Tue, 20 Nov 2007 02:49:24 GMT

In article < XXXX@XXXXX.COM >,

The question mark simply indicates that the duration is a best guess 
estimate. You can remove it under Tools/Options/Schedule. Uncheck the 
option to "show that tasks have estimated durations".

Project MVP

Re: Duration Question Mark

Postby Mike Glen » Tue, 20 Nov 2007 03:07:55 GMT

Incidentally, I forgot to mention that you can type in the duration with a 
question mark to bring it back again.

Mike Glen
Project MVP

Re: Duration Question Mark

Postby cassidym » Tue, 20 Nov 2007 07:07:05 GMT

One more question. Somehow, I've locked my initial task so that it onl
shows it's duration as equal to the combined durations of the subtasks

When I try to extend the finish date of the primary task, I can't ge
the calendar to open. The only way I can extend the time frame is t
add another subtask or extend the last one.

Obviously, I've changed a setting that is enforcing this

Any ideas what I did and how I can rectify it



Re: Duration Question Mark

Postby JulieS » Tue, 20 Nov 2007 10:54:07 GMT

Hello cassidym,

I assume you are talking about the project summary task (line zero). 
You have done nothing incorrect.  Summary task durations are calculated 
by Project and are the span of working time from the start of the 
earliest subtask to the finish of the last subtask.  As you note, the 
only way to change the duration is to change the schedule of the 

I hope this helps.  Let us know how you get along.

Project MVP

Visit  http://www.**--****.com/ 
about Microsoft Project

Similar Threads:

1.Question mark in Task Duration

Can anyone help with this simple problem?

Why does the Duration box in the Task Form have a question mark after
the estimated duration?

Typically I enter new tasks in the Task Form. My default Task Type set
to Fixed Work. I assign a Resource and enter the Work in the fields
provided. If the resource is not fully available, I adjust the Units.
The Duration box then gives me an estimate of how long the task will
take to complete. Nice. For example a 1 day task assigned to a 20%
resourse will take 5d to complete. But Project displays "5d?"  I don't
understand why sometimes there is a ? after the duration estimate and
sometimes not. Any ideas? 


2.Red mark and blue mark in timesheet hrs


For some of the task hrs in timesheet, the hrs shows red and for some the 
hrs shows blue color.

I understood that for approved ones the hrs shows black color. But, what it 
indicates when the task hrs shows red and blue color.

Any thoughts on this would be greatly appreciated.

Thank you
Shiva Chaitanya. 

3.Sub Task showing Days and Question Mark

4.? mark in Duration

I know this is a stupid question, but why do the ? marks show up in a 
duration? How can I get them to default to not showing up? How do I remove 
exisiting ones. I have just taken over a file from a client tha tis filled 
with them and Im on a time contraint.
I knowits some simple function that I am overlooking

5.What is the purpose of the question mark (?) in the duration field?

What is the purpose of the question mark (?) in the 
duration field? I know it is used to indicate an 
estimate.  Is that the only purpose - just an indicator?  
Does it server any other purpose or control how MS Project 
works in any way?

6. What is the purpose of the question mark (?) in the duration field

7. Fixed Duration Question

8. duration question

Return to Microsoft Project


Who is online

Users browsing this forum: No registered users and 14 guest