Can A Sub Project's Duration Be Changed?

Microsoft Project

    Next

  • 1. organizing gantt chart and network diagram so it's easily managed
    Is there a way to automatically arrange tasks so that the gantt chart isn't so chaotic? Like arranging the tasks such that it looks more like stairs, stepping from the first task to the very last task. Similar question for the netwrok diagram. Overlapping lines make the diagram very confusing. Is it possible to force overlaping lines to bend or something else that helps distinguish the lines?
  • 2. Toggling resources
    As I assign the resource to the task, that source is displayed next to the task bar in the project schedule. What I want to do is toggle this resources assignment on/off, meaning that at one point I want to see the tasks and their resources and the next view would be just a task. thanks
  • 3. Resource Pools and templates
    I have set up a resource pool file to use for each new project. I am using a template to create the individual projects. Is there a way that I can modify my template so that the files created from it will automatically resource share using my resource pool file? Thanks Janet
  • 4. Project Start Date keeps changing when Actual Start Date changes
    Hello, I guess I have made some mistakes when creating the project in Project 2003. In the project, I have columns "Start","Finish","Actual Start" & "Actual Finish" and etc. "Start" column lists the date when the task is supposed to start and "Actual Start" column lists the date when the task actually starts. The problem is that whenever I change the date under "Actual Start" column to anything from NA, the date value under "Start" column changes as well. In summary, "Start" date changes whenever "Actual Start" date changes. Can anybody let me know what I did wrong and how I can solve this annoying issue? Thanks a million.
  • 5. 8.5 x 14 doc won't print full page. Already changed page setup.
    I have created a 8.5 x 14 landscape document and changed all the settings in page set up. When I try to print the document, it will not print full page.

Can A Sub Project's Duration Be Changed?

Postby Q2hyaXMgTW9sbGFuZA » Thu, 20 Dec 2007 07:44:01 GMT

Hello,

I would be grateful if someone could explain how to perform the following 
(if it can be done at all!)

I wish to prepare a selection of library Projects, each with a few Tasks and 
their associated Resources etc. Perhaps these could be saved as Templates. I 
then will create a Master project file and insert items from my library. I 
have called these sub-projects.

If I insert a sub-project which when defined had 3 Tasks and the total 
duration for the sub-project was, for example, 4 days - can I select the 
sub-project and override the total duration to 6 days. In effect stretching 
the individual Tasks proportionally?

I want to allow a user to pick from the library sub-projects which have been 
pre-defined in terms of Tasks and Resources but allow a global stretch or 
shrink of the sub-project duration based on experience at the time it is 
inserted into the Master project file.

Thank you.

Re: Can A Sub Project's Duration Be Changed?

Postby Jack Dahlgren » Thu, 20 Dec 2007 09:04:11 GMT

To change the project duration, you need to adjust the individual tasks. The 
summary reflects the durations of the tasks below it.

-Jack Dahlgren








Similar Threads:

1.Task Duration (days) Sub-task Duration (wks)

How do I change the task duration to weeks as I am showing the subtask in 
weeks.
I am being restricted to days on the original task as I indent the subtasks.

2.Canned Project server 2003 reports?

Does anyone produce a set of pre-canned Enterprise Project reports for
Project server 2003? We would like to put up a number of reports for
our executives to access through the web interface. PS2003 doesnt seem
to have anything built-in. I know we can run reports out of project
itself - but they are not dynamic.
Does anyone publish templates/add-ins that do this? We are trying to
get a head start with some basic reports that we can modify.

Al Blake, Australia

3.Sub-sub tasks under sub-tasks

4.I am getting decimals for my duration.

When I entered my project information, the start and finish dates were not 
matching the duration which was in days. So I went into Tools>Options, 
Calendar tab and fixed that information to 8 hours a day, 40 hours a week, 
and the week starts on Monday. This fixed my start and finish day but once I 
changed this information, the duration changed to decimals. For example, 3 
days changed to 2.73, 6 days changed to 5.45. 
Why does it change the duration to decimals and how can I fix it?

Thanks for your help

5.Pls tell me immediately i am in problem (whole values change in decimals in project automatically)

Hi,

I am facing an error .

I made a vacations report in sql server reporting services.
and it is working correctly and showing correct vacations but now it is
showing again a wrong result . and when I open a project of vacation from
project professional i see different entries in different dates in resource
usage view . i see entries in decimal instead of whole numbers.

I astonish how It can happen.
pls tell me the problem .

regards

Micheal


6. Link tasks between sub projects with duration?

7. Want to change project work without changing duration

8. How do I change from AM/PM scale to military time in MS Projec



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 91 guest