change the legend in Project

Microsoft Project

    Sponsored Links

    Next

  • 1. microsoft project combined with sage timberline
    looking for something to intergrate project with sage timberline accounting for tracking multipul construction projects at the University of Manitoba...told by sage no can do? I know I need to upgrade project (currently have 2003 want 2007) and get my own server (can i piggyback on the one they have for timberline?) but is there something out there to combine the two or what upgrades do I need.
  • 2. print the Calendar View in Microsoft Project 2003 with resources
    I would like to print a calendar view document with tasks and associated resources.
  • 3. Formula using both date and %complete
    I want to use a column that is a graphical light indicator based on current date, start date, and %complete. I've read other questions on this thread, and read the info provided in links on how to setup custom fields, however, my current formula is not working correctly. I want to use an indicator which changes color based on the following: if [(current date - 5d) > current date] and (%complete <100) then "red" if [(current date - 5d) <= current date] or (%complete = 100) then "green" I've tried this formula, but sub-task graphical indicators don't always appear: IIf([% Complete]<100 And ([Start]<ProjDateValue([Current Date]-5)),"RED",IIf([% Complete]=100 or ([Start]>=ProjDateValue([Current Date]-5)),"GREEN") Thanks for you help. Jeff
  • 4. difference b/w % work complete and % complete???
    hi, can anyone tell me what the difference is b/w '% work complete' and '% complete' columns in ms project? was a bit confused and couldnt find that in project help. thanks. Farooq Khan
  • 5. Consolidating Master Plan
    Hello, I have a Master plan with 5 subplans in it (some with up to 10,000 lines). There are also predecessors between the five plans (done by referencing their path then line number - ie C:/subplan.mpp/834). I was wondering how I could make all these references static - I want a snapshot of the entire plan to send to management that does not force them to load five different plans. If I go to Task Information -> Advanced -> and uncheck "Link to Project" for the five subplans, it still wants to open them when it loads due to the predecessors. How can I make a copy of this plan static and keep my predecessors between the plans? Thank you, Hugh

change the legend in Project

Postby SmhhbGw » Sat, 11 Jun 2005 07:57:01 GMT

I know I was able to change the items in the legend before, but I can't 
remember now.

I need to delete some of the legend items in my Gantt chard that are not 
used in the actual schedule. To avoid confusion 

Re: change the legend in Project

Postby Jim Spiller » Sat, 11 Jun 2005 08:38:29 GMT

Go to Format-Bar Styles and put an asterisk (*) before the Name of the ones 
that you don't want to appear in the legend.

Or delete them...









Similar Threads:

1.Printing: Change the large legend

Hello

Is it possible to alter the legend to display my own task types (like the
defailt Task and External task etc). I have several different ones and need
them in that box somehow.

Thanks in advance

Jon

PS Not the legend that displays the project name and date, the one to the
right of that.


2.How do I change the legend

How do I change the type of bars next to the legend and the footer. They are 
not part of either. Please let me know.

Thanks,

3.change legend titles

How does one change legend titles
-- 
BJO

4.can i change what symbols appear in the legend

how do i change what symbols that appear in the legend in the network diagram 
view in project? 

5.change the task bar symbols in the legend

Does anyone know how or if you are even able to change the task bar symbols 
in a format that will show the change within the legend????

6. changing the legend

7. Changing bar styles in legend at bottom of Gantt chart report

8. Changing the "Legend"



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 88 guest