change the legend in Project

Microsoft Project

    Sponsored Links

    Next

  • 1. incorrect eac in ms project
    The tasks i enter in to the project after my baseline have been save show a incorrect EAC why is this and how can it be fixed? if i save a second baseline and use that for the earned value calculations the figure is rediculously high for the actual cost and the percent complete.
  • 2. "Actual work" values change when zooming in and out
    I am entering actual work values in the Task Usage view, in the assignment rows. For tracking purposes, I am entering weekly values. However, if I zoom in to days (or even the 3-day level, then when I zoom out again, the original values have been "corrupted". I suspect it is something to do with how MS Project distrubutes the input data across days, and then "rebuilds" the weekly totals from these when zooming back out. Also, that it will be to do with in what unit work is stored as (hours/days). I know that one can set the option for the project "Work entered in:", but in my organisation, we receive actuals in hours, but weekly.
  • 3. % complete vs %wok complete vs physical % complete
    i will highly appreciate if some one can explain to me with some good example that what is difference between % complete, %wok complete and physical % complete. thanks
  • 4. Project 2003 login to project server 2003 issue
    Hey, Has anyone else run into an issue with loging into a project server and the server won't validate a known login? This is causing the copy of project 2003 on the win xp box to be unuseable, as it only will close when it does not authenticate against the server. There seems to be no way to change the login. I can login from other copies of project 2003 to the server still. Any good ideas? Thanks TRC
  • 5. Project server throhgt Isa server 2004
    How to publishing Project Server 2003 through Isa server 2004??

change the legend in Project

Postby SmhhbGw » Sat, 11 Jun 2005 07:57:01 GMT

I know I was able to change the items in the legend before, but I can't 
remember now.

I need to delete some of the legend items in my Gantt chard that are not 
used in the actual schedule. To avoid confusion 

Re: change the legend in Project

Postby Jim Spiller » Sat, 11 Jun 2005 08:38:29 GMT

Go to Format-Bar Styles and put an asterisk (*) before the Name of the ones 
that you don't want to appear in the legend.

Or delete them...









Similar Threads:

1.Printing: Change the large legend

Hello

Is it possible to alter the legend to display my own task types (like the
defailt Task and External task etc). I have several different ones and need
them in that box somehow.

Thanks in advance

Jon

PS Not the legend that displays the project name and date, the one to the
right of that.


2.How do I change the legend

How do I change the type of bars next to the legend and the footer. They are 
not part of either. Please let me know.

Thanks,

3.change legend titles

How does one change legend titles
-- 
BJO

4.can i change what symbols appear in the legend

how do i change what symbols that appear in the legend in the network diagram 
view in project? 

5.change the task bar symbols in the legend

Does anyone know how or if you are even able to change the task bar symbols 
in a format that will show the change within the legend????

6. changing the legend

7. Changing bar styles in legend at bottom of Gantt chart report

8. Changing the "Legend"



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 39 guest