change the legend in Project

Microsoft Project

    Sponsored Links

    Next

  • 1. Custom Views (Project Professional 2007)
    Hi, my company is using Project Professional and Project Server 2007. We have created two custom views in Project Professional and ever now and then the views some how get mixed up. For example, we've made Table A and Table B and put Table A in view A and Table B in view B. Some how Table B ends up being the view for View A instead of Table A. At first we thought maybe one of the PMs was accidently changing the view but it has also done it over night when no one had been working on it. Have you ever heard of such a glitch?
  • 2. Changing Holiday in Enterprise Global
    Does MS Project 2007 automatically flag a holiday that falls on the weekend to the prior/following work day or is this something that I can change? Example, July 4, 2010 was marked as a holiday, but it is showing up as July 5 being a non-working day for the holiday. The same thing happens for Christmas
  • 3. Lose of Resource Assignment on Task
    I have a PM who has a plan that keeps losing the resource assignments for multiple work resources (both enterprise and generic) on tasks. Can you explain why this may be happening?
  • 4. Setting week numbers
    I would like to set week numbers on a programme from a specific date of my choosing rather than project start or end or from fiscal or calendar year dates. Is this possible -- GDD
  • 5. moving a set point
    I am trying to plan a project in MSP 2003 and I want all tasks to revolve around a milestone. This milestone has predessors and sucsessors. I want to drag the milestone to the left and right and have all connected tasks move with it keeping the same number of days between the tasks both in front and behind. i.e. the milestone has a task that has to happen 2 weeks before and some that have to happen 6 weeks. Also there are tasks that have to happen 3 weeks after etc etc. I have around 30 predessors and 25 sucsessors, i.e. a lot of dependances. What is the easiest way to do this? Many thanks for the help Ben

change the legend in Project

Postby SmhhbGw » Sat, 11 Jun 2005 07:57:01 GMT

I know I was able to change the items in the legend before, but I can't 
remember now.

I need to delete some of the legend items in my Gantt chard that are not 
used in the actual schedule. To avoid confusion 

Re: change the legend in Project

Postby Jim Spiller » Sat, 11 Jun 2005 08:38:29 GMT

Go to Format-Bar Styles and put an asterisk (*) before the Name of the ones 
that you don't want to appear in the legend.

Or delete them...









Similar Threads:

1.Printing: Change the large legend

Hello

Is it possible to alter the legend to display my own task types (like the
defailt Task and External task etc). I have several different ones and need
them in that box somehow.

Thanks in advance

Jon

PS Not the legend that displays the project name and date, the one to the
right of that.


2.How do I change the legend

How do I change the type of bars next to the legend and the footer. They are 
not part of either. Please let me know.

Thanks,

3.change legend titles

How does one change legend titles
-- 
BJO

4.can i change what symbols appear in the legend

how do i change what symbols that appear in the legend in the network diagram 
view in project? 

5.change the task bar symbols in the legend

Does anyone know how or if you are even able to change the task bar symbols 
in a format that will show the change within the legend????

6. changing the legend

7. Changing bar styles in legend at bottom of Gantt chart report

8. Changing the "Legend"



Return to Microsoft Project

 

Who is online

Users browsing this forum: No registered users and 27 guest